Safal Sky Redevelopment Of Ameya Chs Ltd, Chembur
Lapsed
by Varun Homes Pvt Ltd · Chembur, Mumbai 400071 · Map
- Launched
- Aug 20173 yrs originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 5 yrs 4 mthsWhat does Lapsed mean?
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 37 of 4582% · 36 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale37 booked out of 45 units
Rehab36 units for existing members
Total 81 units. Rehab units are not for sale.
Project facts
- 1 RK
- 5
- 2 BHK
- 24
- 3 BHK
- 52
- Total units
- 81
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 45
- Rehab units
- 36
- Reserved units
- 5
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 50% | 37 | |
| 100% | 90% | 0% | 37 | |
| 100% | 85% | 50% | 37 | |
| 100% | 85% | 50% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400071
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs | 2 yrs 1 mth |
| Possession date extended | By 5 yrs 4 mths | 6 of 6 |
| Possession date (MahaRERA) | Dec 2025 | Dec 2022 |
| Concrete structure (RCC) | 90% | 100% |
| Units booked (free sale) | 82% | 95% |
| MahaRERA complaints (filed by or against the builder) | 1 | 7 |
The 6 projects
- Guruprasad Divine Residency, Chembur
- Rite Skyluxe, Chembur
- Tridhaatu Aranya, Chembur
- Odina, Chembur
- Srushti Enclave, Chembur
- Hubtown Seasons - B Wing, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Guruprasad Divine Residency | August 2017 | June 2020 | 85% | 58 units booked out of 62 units for sale |
| Rite Skyluxe | August 2017 | December 2020 | 94% | – |
| Tridhaatu Aranya | August 2017 | December 2024 | 100% | 54 units booked out of total 63 units |
| Odina | August 2017 | March 2020 | 100% | – |
| Srushti Enclave | August 2017 | December 2025 | 100% | 35 units booked out of 35 units for sale |
| Hubtown Seasons - B Wing | August 2017 | July 2026 | 100% | 51 units booked out of total 53 units |
About this project
Safal Sky Redevelopment Of Ameya Chs Ltd by Varun Homes Pvt Ltd is an 81-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in August 2017; its MahaRERA registration has lapsed. 37 units booked out of 45 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Safal Sky Redevelopment Of Ameya Chs Ltd is a BMC-sanctioned project by Varun Homes Pvt Ltd in Chembur, Mumbai 400071, registered with MahaRERA as P51800004137. It was launched in August 2017. It has 81 units in 1 building, with 1 RK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 81 units, 45 are for sale and 36 are rehab units for existing members.
Possession was due in December 2025, after an extension of 5 years 4 months from the original August 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 90% complete, final finishes 50% complete.
37 units booked out of 45 units for sale (82%).