Srushti Enclave, Chembur

Ready to moveLapsed

by Gadkari Builders & Associates · Chembur, Mumbai 400071 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 6 yrsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
35 of 35100% · 14 rehab units
Buildings
10.2 acres
MahaRERA complaints
12Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale35 booked out of 35 units

Rehab14 units for existing members

Land-owner share10 units, not for sale

Total 59 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
1
2 BHK
57
Other units
1
Total units
59
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
12
Free-sale units
35
Rehab units
14
Land-owner share (not for sale)
10
Reserved units
5

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 87%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 50%Dec 2025: Final finishes 85%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%35
100%100%100%35
100%100%85%35
100%87%50%35

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths4 yrs 8 mths
Possession date extendedBy 6 yrs6 of 6
Possession date (MahaRERA)Dec 2025Jun 2025
Concrete structure (RCC)100%95%
Units booked (free sale)100%86%
MahaRERA complaints (filed by or against the builder)120

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Srushti Enclave by Gadkari Builders & Associates is a 59-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in August 2017; its MahaRERA registration has lapsed. 35 units booked out of 35 units for sale. The concrete structure (RCC) is complete.

Read full summary

Srushti Enclave is a BMC-sanctioned project by Gadkari Builders & Associates in Chembur, Mumbai 400071, registered with MahaRERA as P51900011095. It was launched in August 2017. It has 59 units in 1 building: 58 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 59 units, 35 are for sale, 14 are rehab units for existing members and 10 are the land-owner's share, not for sale.

Possession was due in December 2025, after an extension of 6 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

35 units booked out of 35 units for sale (100%).