Guruprasad Divine Residency, Chembur
Lapsed
by Rohinton Mehta Builders And Developers · Chembur, Mumbai 400071 · Map
- Launched
- Aug 20171 yr 10 mths originally promised
- Possession (MahaRERA)
- Jun 2020Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 85%Mid-construction
- Booked (free sale)
- 58 of 6294% · 32 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale58 booked out of 62 units
Rehab32 units for existing members
Total 94 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 26
- 2 BHK
- 13
- 3 BHK
- 41
- Other units
- 14
- Total units
- 94
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 3
- Free-sale units
- 62
- Rehab units
- 32
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 85% | 85% | 50% | 58 | |
| 85% | 85% | 50% | – | |
| 85% | 85% | 50% | 17 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400071
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 10 mths | 2 yrs 8 mths |
| Possession date extended | By 1 yr | 6 of 6 |
| Possession date (MahaRERA) | Jun 2020 | Jun 2025 |
| Concrete structure (RCC) | 85% | 100% |
| Units booked (free sale) | 94% | 91% |
| MahaRERA complaints (filed by or against the builder) | 3 | 6 |
The 6 projects
- Safal Sky Redevelopment Of Ameya Chs Ltd, Chembur
- Rite Skyluxe, Chembur
- Tridhaatu Aranya, Chembur
- Srushti Enclave, Chembur
- Odina, Chembur
- Hubtown Seasons - B Wing, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Safal Sky Redevelopment Of Ameya Chs Ltd | August 2017 | December 2025 | 90% | 37 units booked out of 45 units for sale |
| Rite Skyluxe | August 2017 | December 2020 | 94% | – |
| Tridhaatu Aranya | August 2017 | December 2024 | 100% | 54 units booked out of total 63 units |
| Srushti Enclave | August 2017 | December 2025 | 100% | 35 units booked out of 35 units for sale |
| Odina | August 2017 | March 2020 | 100% | – |
| Hubtown Seasons - B Wing | August 2017 | July 2026 | 100% | 51 units booked out of total 53 units |
About this project
Guruprasad Divine Residency by Rohinton Mehta Builders And Developers is a 94-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in August 2017; its MahaRERA registration has lapsed. 58 units booked out of 62 units for sale. The concrete structure (RCC) is 85% complete.
Read full summary
Guruprasad Divine Residency is a BMC-sanctioned project by Rohinton Mehta Builders And Developers in Chembur, Mumbai 400071, registered with MahaRERA as P51900009197. It was launched in August 2017. It has 94 units in 1 building: 80 homes (1, 2 and 3 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 94 units, 62 are for sale and 32 are rehab units for existing members.
Possession was due in June 2020, after an extension of 1 year from the original June 2019. That date has passed and no further extension has been recorded. Construction: excavation 85% complete, structure (RCC) 85% complete, final finishes 50% complete.
58 units booked out of 62 units for sale (94%).