Shreeji Atlantis, Malad West
by Shreeji Construction · Malad West, Mumbai 400064 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2027Extended in both phases
- Concrete structure
- 72%Weighted across 2 phases
- Booked
- –
- Buildings
- 21.7 acres
- MahaRERA complaints
- 17Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 303
- 3 BHK
- 81
- Other units
- 12
- Total units
- 396
- Buildings
- 2
- Land
- 1.7 acres
- Phases
- 2
- MahaRERA complaints
- 17
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Shreeji Atlantis Wing A Completed | P51800004400 | 186 | 100% | – | |
| Shreeji Atlantis Wing B Mid-construction | P51800047335 | 198 | 46% | 63% |
Show updates by phase
Shreeji Atlantis Wing A (P51800004400)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 171 |
"–" means MahaRERA shows no figure for that update.
Shreeji Atlantis Wing B (P51800047335)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 46% | 0% | 131 | |
| 100% | 35% | 0% | 129 | |
| 100% | 5% | 0% | 124 | |
| 100% | 2% | 0% | 101 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 6 similar projects in PIN 400064
Projects with 150–800 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 3 mths | 6 yrs 7 mths |
| Possession date extended | Yes | 3 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Nov 2025 |
| Concrete structure (RCC) | 72% | 80% |
| Units booked | – | 65% |
| MahaRERA complaints (filed by or against the builder) | 17 | 21 |
The 6 projects
- Shreeji Plaza, Malad West
- Linkpark, Malad West
- Adhrit, Malad West
- Sky Tower, Malad West
- Rajinfinia Phase II Wing A Wing B Wing C, Malad West
- Auris Serenity, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shreeji Plaza | August 2017 | Sep 2026 | 100% | 293 units booked out of total 365 units |
| Linkpark | August 2017 | October 2026 | 0% | 182 units booked out of total 324 units |
| Adhrit | August 2017 | April 2027 | 80% | 128 units booked out of 175 units for sale |
| Sky Tower | August 2017 | December 2023 | 0% | 84 units booked out of total 247 units |
| Rajinfinia Phase II Wing A Wing B Wing C | September 2017 | December 2024 | 80% | – |
| Auris Serenity | July 2017 | Dec 2024 | 100% | – |
About this project
Shreeji Atlantis by Shreeji Construction is a 396-unit SRA-sanctioned project in Malad West, Mumbai 400064, registered with MahaRERA in 2 phases, with possession due in December 2027. The concrete structure (RCC) is 72% complete.
Read full summary
Shreeji Atlantis is an SRA-sanctioned project by Shreeji Construction in Malad West, Mumbai 400064, registered with MahaRERA as 2 phases (P51800004400, P51800047335). The first phase was launched in August 2017. Together the phases have 396 units in 2 buildings: 384 homes (2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.
The registered possession date is December 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 72% complete and final finishes 48% complete. Neither phase has its structure complete.