Shreeji Atlantis, Malad West

by Shreeji Construction · Malad West, Mumbai 400064 · Map

Launched
Aug 2017First of 2 phases
Possession (MahaRERA)
Dec 2027Extended in both phases
Concrete structure
72%Weighted across 2 phases
Booked
–
Buildings
21.7 acres
MahaRERA complaints
17Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
303
3 BHK
81
Other units
12
Total units
396
Buildings
2
Land
1.7 acres
Phases
2
MahaRERA complaints
17

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Shreeji Atlantis Wing A
Completed
P51800004400186100%–
Shreeji Atlantis Wing B
Mid-construction
P5180004733519846%63%
Show updates by phase

Shreeji Atlantis Wing A (P51800004400)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%171

"–" means MahaRERA shows no figure for that update.

Shreeji Atlantis Wing B (P51800047335)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%46%0%131
100%35%0%129
100%5%0%124
100%2%0%101

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)72%
Finishes, lifts and services48%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 49%Dec 2025: Concrete structure (RCC) 51%Jul 2026: Concrete structure (RCC) 66%Oct 2026: Concrete structure (RCC) 72%Dec 2024: Final finishes 48%Dec 2025: Final finishes 48%Jul 2026: Final finishes 48%Oct 2026: Final finishes 48%Excavation 100%Concrete structure (RCC) 72%Final finishes 48%

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths6 yrs 7 mths
Possession date extendedYes3 of 6
Possession date (MahaRERA)Dec 2027Nov 2025
Concrete structure (RCC)72%80%
Units booked–65%
MahaRERA complaints (filed by or against the builder)1721

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shreeji Atlantis by Shreeji Construction is a 396-unit SRA-sanctioned project in Malad West, Mumbai 400064, registered with MahaRERA in 2 phases, with possession due in December 2027. The concrete structure (RCC) is 72% complete.

Read full summary

Shreeji Atlantis is an SRA-sanctioned project by Shreeji Construction in Malad West, Mumbai 400064, registered with MahaRERA as 2 phases (P51800004400, P51800047335). The first phase was launched in August 2017. Together the phases have 396 units in 2 buildings: 384 homes (2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.

The registered possession date is December 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 72% complete and final finishes 48% complete. Neither phase has its structure complete.