Shreeji Plaza, Malad West
Ready to moveLapsed
by Siddharth Enterprises · Malad West, Mumbai 400064 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Sep 2026Extended in both phasesWhat does Lapsed mean?
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- 293 of 36580% · 280 in Jul 2026
- Buildings
- 21.8 acres
- MahaRERA complaints
- 7Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 261
- 2 BHK
- 103
- Other units
- 1
- Total units
- 365
- Buildings
- 2
- Land
- 1.8 acres
- Phases
- 2
- MahaRERA complaints
- 7
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Shreeji Plaza Wing A Ready to move Lapsed | P51800007051 | 165 | 100% | 80% | |
| Shreeji Plaza Wing B Ready to move Lapsed | P51800011168 | 199 | 100% | 80% |
Show updates by phase
Shreeji Plaza Wing A (P51800007051)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 132 | |
| 100% | 100% | 30% | 128 | |
| 100% | 100% | 0% | 127 | |
| 100% | 64% | 0% | 108 |
"–" means MahaRERA shows no figure for that update.
Shreeji Plaza Wing B (P51800011168)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 96% | 161 | |
| 100% | 100% | 36% | 152 | |
| 100% | 100% | 0% | 149 | |
| 100% | 64% | 0% | 130 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 6 similar projects in PIN 400064
Projects with 150–800 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 10 mths | 6 yrs 4 mths |
| Possession date extended | Yes | 3 of 6 |
| Possession date (MahaRERA) | Sep 2026 | Nov 2025 |
| Concrete structure (RCC) | 100% | 76% |
| Units booked | 80% | 56% |
| MahaRERA complaints (filed by or against the builder) | 7 | 26 |
The 6 projects
- Shreeji Atlantis, Malad West
- Linkpark, Malad West
- Adhrit, Malad West
- Sky Tower, Malad West
- Rajinfinia Phase II Wing A Wing B Wing C, Malad West
- Auris Serenity, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shreeji Atlantis | August 2017 | Dec 2027 | 72% | – |
| Linkpark | August 2017 | October 2026 | 0% | 182 units booked out of total 324 units |
| Adhrit | August 2017 | April 2027 | 80% | 128 units booked out of 175 units for sale |
| Sky Tower | August 2017 | December 2023 | 0% | 84 units booked out of total 247 units |
| Rajinfinia Phase II Wing A Wing B Wing C | September 2017 | December 2024 | 80% | – |
| Auris Serenity | July 2017 | Dec 2024 | 100% | – |
About this project
Shreeji Plaza by Siddharth Enterprises is a 365-unit SRA-sanctioned project in Malad West, Mumbai 400064, registered with MahaRERA in 2 phases, with possession due in September 2026. 293 units booked out of total 365 units. The concrete structure (RCC) is complete.
Read full summary
Shreeji Plaza is an SRA-sanctioned project by Siddharth Enterprises in Malad West, Mumbai 400064, registered with MahaRERA as 2 phases (P51800007051, P51800011168). The first phase was launched in August 2017. Together the phases have 365 units in 2 buildings: 364 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Both phases are lapsed on MahaRERA.
The registered possession date is September 2026; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 98% complete. Both phases have their structure complete.
293 units booked out of total 365 units (80%). Since the July 2026 update, 13 more units have been booked.