Adhrit, Malad West
by Mundara Developers · Malad West, Mumbai 400064 · Map
- Launched
- Aug 20176 yrs 2 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 6 mths
- Concrete structure
- 80%Mid-construction
- Booked (free sale)
- 128 of 17573% · 253 rehab units
- Buildings
- 51.9 acres
- MahaRERA complaints
- 6Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale128 booked out of 175 units
Rehab253 units for existing members
Land-owner share44 units, not for sale
Total 472 units. Rehab and land-owner units are not for sale.
Project facts
- 1 RK
- 207
- 1 BHK
- 64
- 2 BHK
- 132
- 3 BHK
- 65
- Other units
- 4
- Total units
- 472
- Buildings
- 5
- Land
- 1.9 acres
- Phases
- 1
- MahaRERA complaints
- 6
- Free-sale units
- 175
- Rehab units
- 253
- Land-owner share (not for sale)
- 44
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 75% | 128 | |
| 100% | 80% | 75% | 128 | |
| 100% | 80% | 74% | 128 | |
| 100% | 78% | 64% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400064
Projects with 200–1,000 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 2 mths | 6 yrs 10 mths |
| Possession date extended | By 3 yrs 6 mths | 3 of 6 |
| Possession date (MahaRERA) | Apr 2027 | May 2026 |
| Concrete structure (RCC) | 80% | 76% |
| Units booked (free sale) | 73% | 79% |
| MahaRERA complaints (filed by or against the builder) | 6 | 26 |
The 6 projects
- Shreeji Atlantis, Malad West
- Shreeji Plaza, Malad West
- Linkpark, Malad West
- Rajinfinia Phase II Wing A Wing B Wing C, Malad West
- Auris Serenity, Malad West
- Irene, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shreeji Atlantis | August 2017 | Dec 2027 | 72% | – |
| Shreeji Plaza | August 2017 | Sep 2026 | 100% | 293 units booked out of total 365 units |
| Linkpark | August 2017 | October 2026 | 0% | 182 units booked out of total 324 units |
| Rajinfinia Phase II Wing A Wing B Wing C | September 2017 | December 2024 | 80% | – |
| Auris Serenity | July 2017 | Dec 2024 | 100% | – |
| Irene | March 2018 | Dec 2025 – Oct 2028 | 65% | 507 units booked out of total 643 units |
About this project
Adhrit by Mundara Developers is a 472-unit SRA-sanctioned project in Malad West, Mumbai 400064, launched in August 2017 with possession due in April 2027. 128 units booked out of 175 units for sale. The concrete structure (RCC) is 80% complete.
Read full summary
Adhrit is an SRA-sanctioned project by Mundara Developers in Malad West, Mumbai 400064, registered with MahaRERA as P51800009600. It was launched in August 2017. It has 472 units in 5 buildings: 468 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 472 units, 175 are for sale, 253 are rehab units for existing members and 44 are the land-owner's share, not for sale.
Its registered possession date is April 2027, extended by 3 years 6 months from the original October 2023. Construction: excavation complete, structure (RCC) 80% complete, final finishes 75% complete.
128 units booked out of 175 units for sale (73%).