Arihant Heights, Ghatkopar West
by Arihant Infrastructure Company · Ghatkopar West, Mumbai 400086 · Map
- Launched
- Jan 20183 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 5 yrs 6 mths
- Concrete structure
- 100%Nearing possession
- Booked
- 47 of 10445%
- Buildings
- 10.4 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 59
- 2 BHK
- 41
- Other units
- 4
- Total units
- 104
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 47 | |
| 100% | 100% | 50% | 47 | |
| 100% | 100% | 40% | – | |
| 100% | 100% | 40% | 42 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400086
Projects with 50–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 2 yrs 10 mths |
| Possession date extended | By 5 yrs 6 mths | 6 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Nov 2024 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 45% | 79% |
| MahaRERA complaints (filed by or against the builder) | 3 | 0 |
The 6 projects
- Vighneshwar Cooperative Housing Society Limited, Ghatkopar West
- Ashok Odyssey, Ghatkopar West
- Tivon Park, Ghatkopar West
- Integrated Arya, Ghatkopar West
- Vikram Delite CHSL, Ghatkopar West
- Anchor Residency, Ghatkopar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vighneshwar Cooperative Housing Society Limited | September 2017 | April 2027 | 100% | 40 units booked out of total 52 units |
| Ashok Odyssey | August 2017 | Apr 2028 | 92% | – |
| Tivon Park | August 2017 | Jun 2022 – Apr 2027 | 100% | 126 units booked out of total 126 units |
| Integrated Arya | August 2017 | March 2022 | 88% | 82 units booked out of 102 units for sale |
| Vikram Delite CHSL | July 2018 | December 2028 | 100% | 0 units booked out of 42 units for sale |
| Anchor Residency | July 2017 | December 2021 | 100% | – |
About this project
Arihant Heights by Arihant Infrastructure Company is a 104-unit SRA-sanctioned project in Ghatkopar West, Mumbai 400086, launched in January 2018 with possession due in December 2026. 47 units booked out of total 104 units. The concrete structure (RCC) is complete.
Read full summary
Arihant Heights is an SRA-sanctioned project by Arihant Infrastructure Company in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800015068. It was launched in January 2018. It has 104 units in 1 building: 100 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 5 years 6 months from the original June 2021. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.
47 units booked out of total 104 units (45%).