- Launched
- Aug 20172 yrs 7 mths originally promised
- Possession (MahaRERA)
- Sep 2021Extended by 1 yr 6 mthsWhat does Lapsed mean?
- Concrete structure
- 68%Mid-construction
- Booked
- –
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 3
- 1 BHK
- 11
- 2 BHK
- 48
- 3 BHK
- 8
- Total units
- 70
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 68% | 0% | – | |
| 100% | 68% | 0% | – | |
| 100% | 68% | 0% | 70 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400089
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 7 mths | 4 yrs 7 mths |
| Possession date extended | By 1 yr 6 mths | 5 of 6 |
| Possession date (MahaRERA) | Sep 2021 | Sep 2026 |
| Concrete structure (RCC) | 68% | 75% |
| Units booked | – | 91% |
| MahaRERA complaints (filed by or against the builder) | 0 | 11 |
The 6 projects
- Akshay Paradise, Chembur
- 49 Elina, Chembur
- Srushtiraj Tower, Chembur
- Srushti Raj Siddhi, Chembur
- Basil Residency, Chembur
- Midas-Bhakti Meadows, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Akshay Paradise | August 2017 | December 2025 | 70% | 87 units booked out of total 102 units |
| 49 Elina | August 2017 | December 2020 | 100% | – |
| Srushtiraj Tower | August 2017 | April 2027 | 80% | 93 units booked out of 101 units for sale |
| Srushti Raj Siddhi | August 2017 | April 2028 | 53% | 88 units booked out of 97 units for sale |
| Basil Residency | September 2017 | December 2026 | 0% | 28 units booked out of total 112 units |
| Midas-Bhakti Meadows | October 2017 | May 2026 | 100% | 71 units booked out of total 78 units |
About this project
39 Anthea by Shreenathji Developers Pvt Ltd is a 70-unit project in Chembur, Mumbai 400089, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 68% complete.
Read full summary
39 Anthea is a project by Shreenathji Developers Pvt Ltd in Chembur, Mumbai 400089, registered with MahaRERA as P51800004686. It was launched in August 2017. It has 70 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in September 2021, after an extension of 1 year 6 months from the original March 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 68% complete, final finishes not started.