Midas-Bhakti Meadows, Chembur

Lapsed

by Irene Edwyn Dmello · Chembur, Mumbai 400089 · Map

Launched
Oct 20171 yr 8 mths originally promised
Possession (MahaRERA)
May 2026Extended by 6 yrs 11 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
71 of 7891%
Buildings
10.8 acres
MahaRERA complaints
16Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
26
2 BHK
51
3 BHK
1
Total units
78
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 10%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 100%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%71
100%100%10%71
100%100%0%67
100%90%0%60

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400089

Projects with 30–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400089
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 8 mths4 yrs 7 mths
Possession date extendedBy 6 yrs 11 mths5 of 6
Possession date (MahaRERA)May 2026Jun 2026
Concrete structure (RCC)100%69%
Units booked91%88%
MahaRERA complaints (filed by or against the builder)166

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Midas-Bhakti Meadows by Irene Edwyn Dmello is a 78-unit SRA-sanctioned project in Chembur, Mumbai 400089, launched in October 2017; its MahaRERA registration has lapsed. 71 units booked out of total 78 units. The concrete structure (RCC) is complete.

Read full summary

Midas-Bhakti Meadows is an SRA-sanctioned project by Irene Edwyn Dmello in Chembur, Mumbai 400089, registered with MahaRERA as P51800013457. It was launched in October 2017. It has 78 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in May 2026, after an extension of 6 years 11 months from the original June 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.

71 units booked out of total 78 units (91%).