Gauri Excellency, Kandivali West

Lapsed

by M/S Gauri Land Developers LLP · Kandivali West, Mumbai 400067 · Map

Launched
Aug 20173 yrs 4 mths originally promised
Possession (MahaRERA)
Jun 2026Extended by 5 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
31%Mid-construction
Booked (free sale)
309 of 309100%
Buildings
13 acres
MahaRERA complaints
8Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale309 booked out of 309 units

Land-owner share6 units, not for sale

Total 315 units. Land-owner units are not for sale.

Project facts

1 BHK
104
2 BHK
200
Other units
11
Total units
315
Buildings
1
Land
3 acres
Phases
1
MahaRERA complaints
8
Free-sale units
309
Land-owner share (not for sale)
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)31%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 31%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 31%Oct 2026: Concrete structure (RCC) 31%Dec 2024: Final finishes 90%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Final finishes 95%Concrete structure (RCC) 31%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%31%95%309
100%31%95%309
100%100%95%307
100%31%90%296

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths4 yrs 9 mths
Possession date extendedBy 5 yrs 6 mths4 of 6
Possession date (MahaRERA)Jun 2026Dec 2024
Concrete structure (RCC)31%56%
Units booked (free sale)100%65%
MahaRERA complaints (filed by or against the builder)822

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Gauri Excellency by M/S Gauri Land Developers LLP is a 315-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in August 2017; its MahaRERA registration has lapsed. 309 units booked out of 309 units for sale. The concrete structure (RCC) is 31% complete.

Read full summary

Gauri Excellency is an SRA-sanctioned project by M/S Gauri Land Developers LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800004832. It was launched in August 2017. It has 315 units in 1 building: 304 homes (1 and 2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 315 units, 309 are for sale and 6 are the land-owner's share, not for sale.

Possession was due in June 2026, after an extension of 5 years 6 months from the original December 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 31% complete, final finishes 95% complete.

309 units booked out of 309 units for sale (100%).