Meridian Court 1, Kandivali West

by Vijaykamal Properties Pvt Ltd · Kandivali West, Mumbai 400067 · Map

Launched
Aug 20177 yrs 4 mths originally promised
Possession (MahaRERA)
Apr 2028Extended by 3 yrs 4 mths
Concrete structure
8%Mid-construction
Booked
221 of 37359%
Buildings
10.2 acres
MahaRERA complaints
26Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
175
2 BHK
176
Other units
22
Total units
373
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)8%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 40%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 8%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 8%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%8%0%221
100%0%0%221
100%0%0%184
40%0%0%41

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)7 yrs 4 mths3 yrs 5 mths
Possession date extendedBy 3 yrs 4 mths5 of 6
Possession date (MahaRERA)Apr 2028Sep 2026
Concrete structure (RCC)8%62%
Units booked59%70%
MahaRERA complaints (filed by or against the builder)2631

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Meridian Court 1 by Vijaykamal Properties Pvt Ltd is a 373-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in August 2017 with possession due in April 2028. 221 units booked out of total 373 units. The concrete structure (RCC) is 8% complete.

Read full summary

Meridian Court 1 is an SRA-sanctioned project by Vijaykamal Properties Pvt Ltd in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800007441. It was launched in August 2017. It has 373 units in 1 building: 351 homes (1 and 2 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2028, extended by 3 years 4 months from the original December 2024. Construction: excavation complete, structure (RCC) 8% complete, final finishes not started.

221 units booked out of total 373 units (59%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 8% and the possession date has moved from December 2025 to April 2028.