Ruparel Westsky, Kandivali West
by Ruparel Shreeji Construction Pvt Ltd · Kandivali West, Mumbai 400067 · Map
- Launched
- Aug 20175 yrs 10 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 4 yrs 6 mths
- Concrete structure
- 58%Mid-construction
- Booked
- 220 of 33665% · 217 in Jul 2026
- Buildings
- 10.8 acres
- MahaRERA complaints
- 51Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 328
- Other units
- 8
- Total units
- 336
- Buildings
- 1
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 51
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 95% | 58% | 0% | 220 | |
| 95% | 51% | 0% | 217 | |
| 95% | 51% | 0% | 217 | |
| 89% | 19% | 0% | 224 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 10 mths | 4 yrs |
| Possession date extended | By 4 yrs 6 mths | 4 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Sep 2024 |
| Concrete structure (RCC) | 58% | 52% |
| Units booked | 65% | 84% |
| MahaRERA complaints (filed by or against the builder) | 51 | 14 |
The 6 projects
- Meridian Court 1, Kandivali West
- Gauri Excellency, Kandivali West
- Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West, Kandivali West
- Kalpavruksh Garden III, Kandivali West
- Dharti Pressidio, Kandivali West
- Ruparel Skygreens I, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Meridian Court 1 | August 2017 | April 2028 | 8% | 221 units booked out of total 373 units |
| Gauri Excellency | August 2017 | June 2026 | 31% | 309 units booked out of 309 units for sale |
| Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali West | August 2017 | December 2019 | 54% | 131 units booked out of total 246 units |
| Kalpavruksh Garden III | August 2017 | June 2021 | 50% | – |
| Dharti Pressidio | September 2017 | December 2022 | 100% | 235 units booked out of total 235 units |
| Ruparel Skygreens I | September 2017 | December 2026 | 100% | 405 units booked out of total 481 units |
About this project
Ruparel Westsky by Ruparel Shreeji Construction Pvt Ltd is a 336-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in August 2017 with possession due in December 2027. 220 units booked out of total 336 units. The concrete structure (RCC) is 58% complete.
Read full summary
Ruparel Westsky is an SRA-sanctioned project by Ruparel Shreeji Construction Pvt Ltd in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800007630. It was launched in August 2017. It has 336 units in 1 building: 328 homes (2 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 4 years 6 months from the original June 2023. Construction: excavation 95% complete, structure (RCC) 58% complete, final finishes not started.
220 units booked out of total 336 units (65%). Since the July 2026 update, 3 more units have been booked, the reported concrete structure (RCC) has gone from 51% to 58% and the possession date has moved from December 2025 to December 2027.
Ruparel's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 28 |
|---|---|
| Total units across these projects | 6,570 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 12 |
| Under construction | 15 |
| Possession date extended on the builder's application | 14 |
| Typical time from launch to 100% structure | 5 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Ruparel projects | 872 (22 of 28 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.