Ruparel Westsky, Kandivali West

by Ruparel Shreeji Construction Pvt Ltd · Kandivali West, Mumbai 400067 · Map

Launched
Aug 20175 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 4 yrs 6 mths
Concrete structure
58%Mid-construction
Booked
220 of 33665% · 217 in Jul 2026
Buildings
10.8 acres
MahaRERA complaints
51Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
328
Other units
8
Total units
336
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
51

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation95%
Concrete structure (slabs)58%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 89%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Oct 2026: Excavation 95%Dec 2024: Concrete structure (RCC) 19%Dec 2025: Concrete structure (RCC) 51%Jul 2026: Concrete structure (RCC) 51%Oct 2026: Concrete structure (RCC) 58%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 95%Concrete structure (RCC) 58%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%58%0%220
95%51%0%217
95%51%0%217
89%19%0%224

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 10 mths4 yrs
Possession date extendedBy 4 yrs 6 mths4 of 6
Possession date (MahaRERA)Dec 2027Sep 2024
Concrete structure (RCC)58%52%
Units booked65%84%
MahaRERA complaints (filed by or against the builder)5114

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ruparel Westsky by Ruparel Shreeji Construction Pvt Ltd is a 336-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in August 2017 with possession due in December 2027. 220 units booked out of total 336 units. The concrete structure (RCC) is 58% complete.

Read full summary

Ruparel Westsky is an SRA-sanctioned project by Ruparel Shreeji Construction Pvt Ltd in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800007630. It was launched in August 2017. It has 336 units in 1 building: 328 homes (2 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 4 years 6 months from the original June 2023. Construction: excavation 95% complete, structure (RCC) 58% complete, final finishes not started.

220 units booked out of total 336 units (65%). Since the July 2026 update, 3 more units have been booked, the reported concrete structure (RCC) has gone from 51% to 58% and the possession date has moved from December 2025 to December 2027.

Ruparel's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA28
Total units across these projects6,570
Completed without extending the possession date0
Completed after an extension1
Lapsed12
Under construction15
Possession date extended on the builder's application14
Typical time from launch to 100% structure5 years 9 months
MahaRERA complaints (filed by or against the builder), all Ruparel projects872 (22 of 28 projects)