Shankeshwar Apartment, Malad East

Ready to move

by Navkar Developers · Malad East, Mumbai 400097 · Map

Launched
Aug 20173 yrs 1 mth originally promised
Possession (MahaRERA)
Apr 2027Extended by 6 yrs 7 mths
Concrete structure
100%Ready to move
Booked
29 of 10627% · 21 in Jul 2026
Buildings
20.5 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
17
2 BHK
49
3 BHK
35
Other units
5
Total units
106
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services98%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 94%Dec 2025: Concrete structure (RCC) 94%Jul 2026: Concrete structure (RCC) 96%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 85%Oct 2026: Final finishes 98%Excavation 100%Concrete structure (RCC) 100%Final finishes 98%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%29
100%96%85%21
100%94%50%–
100%94%50%30

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400097

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth4 yrs 8 mths
Possession date extendedBy 6 yrs 7 mths5 of 6
Possession date (MahaRERA)Apr 2027Dec 2026
Concrete structure (RCC)100%100%
Units booked27%73%
MahaRERA complaints (filed by or against the builder)14

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shankeshwar Apartment by Navkar Developers is a 106-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in August 2017 with possession due in April 2027. 29 units booked out of total 106 units. The concrete structure (RCC) is complete.

Read full summary

Shankeshwar Apartment is a BMC-sanctioned project by Navkar Developers in Malad East, Mumbai 400097, registered with MahaRERA as P51800006116. It was launched in August 2017. It has 106 units in 2 buildings: 101 homes (1, 2 and 3 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2027, extended by 6 years 7 months from the original September 2020. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

29 units booked out of total 106 units (27%). Since the July 2026 update, 8 more units have been booked, the reported concrete structure (RCC) has gone from 96% to 100% and the possession date has moved from September 2021 to April 2027.