- Launched
- Aug 20173 yrs 5 mths originally promised
- Possession (MahaRERA)
- Jun 2025Extended by 4 yrs 5 mthsWhat does Lapsed mean?
- Concrete structure
- 90%Mid-construction
- Booked
- 67 of 9372%
- Buildings
- 13.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 61
- 3 BHK
- 16
- Other units
- 16
- Total units
- 93
- Buildings
- 1
- Land
- 3.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 95% | 90% | 85% | 67 | |
| 95% | 90% | 85% | – | |
| 95% | 90% | 85% | – | |
| 95% | 90% | 85% | 67 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400097
Projects with 30–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 5 yrs 4 mths |
| Possession date extended | By 4 yrs 5 mths | 5 of 6 |
| Possession date (MahaRERA) | Jun 2025 | Feb 2027 |
| Concrete structure (RCC) | 90% | 100% |
| Units booked | 72% | 65% |
| MahaRERA complaints (filed by or against the builder) | 0 | 2 |
The 6 projects
- Sethia Darshan, Malad East
- Sheetal Bhavan, Malad East
- Shankeshwar Apartment, Malad East
- Madhav Reality, Malad East
- Noble Heights, Malad East
- Sheth Blue Ivy, Malad East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sethia Darshan | August 2017 | December 2026 | 100% | 68 units booked out of total 91 units |
| Sheetal Bhavan | August 2017 | June 2023 | 100% | 17 units booked out of total 64 units |
| Shankeshwar Apartment | August 2017 | April 2027 | 100% | 29 units booked out of total 106 units |
| Madhav Reality | August 2017 | November 2023 | 100% | 51 units booked out of total 52 units |
| Noble Heights | August 2017 | April 2028 | 100% | 104 units booked out of total 114 units |
| Sheth Blue Ivy | July 2017 | March 2028 | 3% | 37 units booked out of total 66 units |
About this project
Sugra Park by Blossom Developers is a 93-unit project in Malad East, Mumbai 400097, launched in August 2017; its MahaRERA registration has lapsed. 67 units booked out of total 93 units. The concrete structure (RCC) is 90% complete.
Read full summary
Sugra Park is a project by Blossom Developers in Malad East, Mumbai 400097, registered with MahaRERA as P51800004081. It was launched in August 2017. It has 93 units in 1 building: 77 homes (2 and 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2025, after an extension of 4 years 5 months from the original January 2021. That date has passed and no further extension has been recorded. Construction: excavation 95% complete, structure (RCC) 90% complete, final finishes 85% complete.
67 units booked out of total 93 units (72%).