Sethia Darshan, Malad East

by Sethia Infrastructure Pvt Ltd · Malad East, Mumbai 400097 · Map

Launched
Aug 20177 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 2 yrs
Concrete structure
100%Nearing possession
Booked
68 of 9175%
Buildings
10.4 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
15
2 BHK
57
Other units
19
Total units
91
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 70%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%68
100%100%80%68
100%100%80%65
100%100%70%58

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400097

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)7 yrs 4 mths4 yrs 2 mths
Possession date extendedBy 2 yrs5 of 6
Possession date (MahaRERA)Dec 2026May 2026
Concrete structure (RCC)100%100%
Units booked75%64%
MahaRERA complaints (filed by or against the builder)42

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Sethia Darshan by Sethia Infrastructure Pvt Ltd is a 91-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in August 2017 with possession due in December 2026. 68 units booked out of total 91 units. The concrete structure (RCC) is complete.

Read full summary

Sethia Darshan is a BMC-sanctioned project by Sethia Infrastructure Pvt Ltd in Malad East, Mumbai 400097, registered with MahaRERA as P51800011224. It was launched in August 2017. It has 91 units in 1 building: 72 homes (1 and 2 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

68 units booked out of total 91 units (75%).