Sanskruti Building No 2 C Wing, Malad East
by Nirman Realtors And Developers Ltd · Malad East, Mumbai 400097 · Map
- Launched
- Aug 20178 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 13 of 1681% · 22 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale13 booked out of 16 units
Rehab22 units for existing members
Total 38 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 31
- 2 BHK
- 6
- Other units
- 1
- Total units
- 38
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 3
- Free-sale units
- 16
- Rehab units
- 22
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 13 | |
| 100% | 100% | 0% | 0 | |
| 100% | 100% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400097
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 8 yrs 4 mths | 3 yrs 7 mths |
| Possession date extended | By 1 yr | 6 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Nov 2024 |
| Concrete structure (RCC) | 100% | 58% |
| Units booked (free sale) | 81% | 79% |
| MahaRERA complaints (filed by or against the builder) | 3 | 0 |
The 6 projects
- Sheetal Heights, Malad East
- Vinayak Tower, Malad East
- Maharshi Heights, Malad East
- Shree Sambhav Darshan CHS, Malad East
- Crystal Pride, Malad East
- Madhav Reality, Malad East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sheetal Heights | August 2017 | December 2021 | 10% | 35 units booked out of total 37 units |
| Vinayak Tower | August 2017 | June 2023 | 60% | – |
| Maharshi Heights | August 2017 | December 2028 | 56% | 3 units booked out of total 42 units |
| Shree Sambhav Darshan CHS | August 2017 | December 2025 | 0% | 10 units booked out of total 32 units |
| Crystal Pride | August 2017 | June 2026 | 100% | 26 units booked out of total 33 units |
| Madhav Reality | August 2017 | November 2023 | 100% | 51 units booked out of total 52 units |
About this project
Sanskruti Building No 2 C Wing by Nirman Realtors And Developers Ltd is a 38-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in August 2017 with possession due in December 2026. 13 units booked out of 16 units for sale. The concrete structure (RCC) is complete.
Read full summary
Sanskruti Building No 2 C Wing is an SRA-sanctioned project by Nirman Realtors And Developers Ltd in Malad East, Mumbai 400097, registered with MahaRERA as P51800007436. It was launched in August 2017. It has 38 units in 1 building: 37 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 38 units, 16 are for sale and 22 are rehab units for existing members.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes not started.
13 units booked out of 16 units for sale (81%). Since the July 2026 update, 13 more units have been booked.