Madhav Reality, Malad East
Ready to moveLapsed
by Jayesh Hiralal Gothi · Malad East, Mumbai 400097 · Map
- Launched
- Aug 20174 yrs 10 mths originally promised
- Possession (MahaRERA)
- Nov 2023Extended by 1 yr 5 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 51 of 5298%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 33
- 2 BHK
- 19
- Total units
- 52
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 51 | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | 51 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400097
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 10 mths | 6 yrs 7 mths |
| Possession date extended | By 1 yr 5 mths | 5 of 6 |
| Possession date (MahaRERA) | Nov 2023 | Mar 2026 |
| Concrete structure (RCC) | 100% | 95% |
| Units booked | 98% | 73% |
| MahaRERA complaints (filed by or against the builder) | 0 | 3 |
The 6 projects
- Sheetal Bhavan, Malad East
- Maharshi Heights, Malad East
- Sheetal Heights, Malad East
- Sanskruti Building No 2 C Wing, Malad East
- Sethia Darshan, Malad East
- Sugra Park, Malad East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sheetal Bhavan | August 2017 | June 2023 | 100% | 17 units booked out of total 64 units |
| Maharshi Heights | August 2017 | December 2028 | 56% | 3 units booked out of total 42 units |
| Sheetal Heights | August 2017 | December 2021 | 10% | 35 units booked out of total 37 units |
| Sanskruti Building No 2 C Wing | August 2017 | December 2026 | 100% | 13 units booked out of 16 units for sale |
| Sethia Darshan | August 2017 | December 2026 | 100% | 68 units booked out of total 91 units |
| Sugra Park | August 2017 | June 2025 | 90% | 67 units booked out of total 93 units |
About this project
Madhav Reality by Jayesh Hiralal Gothi is a 52-unit project in Malad East, Mumbai 400097, launched in August 2017; its MahaRERA registration has lapsed. 51 units booked out of total 52 units. The concrete structure (RCC) is complete.
Read full summary
Madhav Reality is a project by Jayesh Hiralal Gothi in Malad East, Mumbai 400097, registered with MahaRERA as P51800004957. It was launched in August 2017. It has 52 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in November 2023, after an extension of 1 year 5 months from the original June 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
51 units booked out of total 52 units (98%).