Premiere by Panache, Chembur
Ready to move
by Panache Developers Pvt Ltd · Chembur, Mumbai 400071 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 4 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 138 of 20667% · 373 rehab units
- Buildings
- 21.1 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale138 booked out of 206 units
Rehab373 units for existing members
Total 579 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 373
- 2 BHK
- 189
- Other units
- 17
- Total units
- 579
- Buildings
- 2
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 206
- Rehab units
- 373
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 97% | 138 | |
| 100% | 99% | 95% | 138 | |
| 100% | 99% | 95% | 138 | |
| 100% | 90% | 83% | 138 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400071
Projects with 250–1,200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 4 mths | 6 yrs 4 mths |
| Possession date extended | By 3 yrs 4 mths | 3 of 4 |
| Possession date (MahaRERA) | Apr 2027 | Jun 2026 |
| Concrete structure (RCC) | 100% | 100% |
| MahaRERA complaints (filed by or against the builder) | 2 | 4 |
The 4 projects
- One Meraki, Chembur
- Safal Trademark, Chembur
- Mass Metropolis, Chembur
- Crystal Armus A to C, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| One Meraki | August 2017 | Dec 2026 | 100% | – |
| Safal Trademark | August 2017 | April 2027 | 100% | 212 units booked out of 230 units for sale |
| Mass Metropolis | September 2017 | December 2025 | 100% | 302 units booked out of 447 units for sale |
| Crystal Armus A to C | July 2017 | December 2023 | 97% | – |
About this project
Premiere by Panache by Panache Developers Pvt Ltd is a 579-unit SRA-sanctioned project in Chembur, Mumbai 400071, launched in August 2017 with possession due in April 2027. 138 units booked out of 206 units for sale. The concrete structure (RCC) is complete.
Read full summary
Premiere by Panache is an SRA-sanctioned project by Panache Developers Pvt Ltd in Chembur, Mumbai 400071, registered with MahaRERA as P51800008982. It was launched in August 2017. It has 579 units in 2 buildings: 562 homes (1 and 2 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 579 units, 206 are for sale and 373 are rehab units for existing members.
Its registered possession date is April 2027, extended by 3 years 4 months from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 97% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
138 units booked out of 206 units for sale (67%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 99% to 100% and the possession date has moved from December 2024 to April 2027.