Safal Trademark, Chembur
by Jai Mata Di Home Construction Pvt Ltd · Chembur, Mumbai 400071 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 4 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 212 of 23092% · 18 rehab units
- Buildings
- 11.1 acres
- MahaRERA complaints
- 31Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale212 booked out of 230 units
Rehab18 units for existing members
Land-owner share4 units, not for sale
Total 252 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 21
- 2 BHK
- 165
- 3 BHK
- 65
- 4 BHK
- 1
- Total units
- 252
- Buildings
- 1
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 31
- Free-sale units
- 230
- Rehab units
- 18
- Land-owner share (not for sale)
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 75% | 212 | |
| 100% | 100% | 80% | 212 | |
| 100% | 100% | 50% | – | |
| 100% | 100% | 50% | 174 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400071
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 4 mths | 5 yrs 4 mths |
| Possession date extended | By 3 yrs 4 mths | 3 of 6 |
| Possession date (MahaRERA) | Apr 2027 | May 2025 |
| Concrete structure (RCC) | 100% | 98% |
| Units booked (free sale) | 92% | 75% |
| MahaRERA complaints (filed by or against the builder) | 31 | 2 |
The 6 projects
- Ruparel Orion, Chembur
- One Meraki, Chembur
- Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71, Chembur
- Safal Sai And Safal Sainath, Chembur
- Premiere by Panache, Chembur
- Crystal Armus A to C, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ruparel Orion | August 2017 | December 2021 | 75% | – |
| One Meraki | August 2017 | Dec 2026 | 100% | – |
| Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71 | August 2017 | January 2021 | 100% | 204 units booked out of total 209 units |
| Safal Sai And Safal Sainath | August 2017 | October 2026 | 63% | 145 units booked out of 193 units for sale |
| Premiere by Panache | August 2017 | April 2027 | 100% | 138 units booked out of 206 units for sale |
| Crystal Armus A to C | July 2017 | December 2023 | 97% | – |
About this project
Safal Trademark by Jai Mata Di Home Construction Pvt Ltd is a 252-unit SRA-sanctioned project in Chembur, Mumbai 400071, launched in August 2017 with possession due in April 2027. 212 units booked out of 230 units for sale. The concrete structure (RCC) is complete.
Read full summary
Safal Trademark is an SRA-sanctioned project by Jai Mata Di Home Construction Pvt Ltd in Chembur, Mumbai 400071, registered with MahaRERA as P51800003754. It was launched in August 2017. It has 252 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 252 units, 230 are for sale, 18 are rehab units for existing members and 4 are the land-owner's share, not for sale.
Its registered possession date is April 2027, extended by 3 years 4 months from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.
212 units booked out of 230 units for sale (92%).