Mass Metropolis, Chembur
Ready to moveLapsed
by Grace Urban Development Corporation · Chembur, Mumbai 400071 · Map
- Launched
- Sep 20177 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 302 of 44768%
- Buildings
- 12.5 acres
- MahaRERA complaints
- 9Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale302 booked out of 447 units
Land-owner share20 units, not for sale
Total 467 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 176
- 2 BHK
- 145
- 3 BHK
- 18
- Other units
- 128
- Total units
- 467
- Buildings
- 1
- Land
- 2.5 acres
- Phases
- 1
- MahaRERA complaints
- 9
- Reserved units
- 11
- Free-sale units
- 447
- Land-owner share (not for sale)
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 302 | |
| 100% | 95% | 95% | – | |
| 100% | 95% | 95% | 233 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400071
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 3 mths | 6 yrs 4 mths |
| Possession date extended | By 1 yr | 2 of 3 |
| Possession date (MahaRERA) | Dec 2025 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| MahaRERA complaints (filed by or against the builder) | 9 | 0 |
The 3 projects
- One Meraki, Chembur
- Premiere by Panache, Chembur
- Crystal Armus A to C, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| One Meraki | August 2017 | Dec 2026 | 100% | – |
| Premiere by Panache | August 2017 | April 2027 | 100% | 138 units booked out of 206 units for sale |
| Crystal Armus A to C | July 2017 | December 2023 | 97% | – |
About this project
Mass Metropolis by Grace Urban Development Corporation is a 467-unit SRA-sanctioned project in Chembur, Mumbai 400071, launched in September 2017; its MahaRERA registration has lapsed. 302 units booked out of 447 units for sale. The concrete structure (RCC) is complete.
Read full summary
Mass Metropolis is an SRA-sanctioned project by Grace Urban Development Corporation in Chembur, Mumbai 400071, registered with MahaRERA as P51800012210. It was launched in September 2017. It has 467 units in 1 building: 339 homes (1, 2 and 3 BHK) and 128 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 467 units, 447 are for sale and 20 are the land-owner's share, not for sale.
Possession was due in December 2025, after an extension of 1 year from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
302 units booked out of 447 units for sale (68%).