- Launched
- Aug 2017First of 3 phases
- Possession (MahaRERA)
- Dec 2026Extended in 1 of 3 phases
- Concrete structure
- 100%Weighted across 3 phases
- Booked
- –
- Buildings
- 40.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 130
- 3 BHK
- 145
- 5+ BHK
- 16
- Total units
- 291
- Buildings
- 4
- Land
- 0.9 acres
- Phases
- 3
- MahaRERA complaints
- 0
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| ONE MERAKI - Wing A & Wing B Completed | P51800011606 | 136 | 100% | – | |
| One Meraki Wing C and Wing D Ready to move | P51800050796 | 139 | 100% | 37% | |
| One Meraki Wing E Ready to move | P51800077475 | 16 | 100% | 12% |
Show updates by phase
ONE MERAKI - Wing A & Wing B (P51800011606)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 96 |
"–" means MahaRERA shows no figure for that update.
One Meraki Wing C and Wing D (P51800050796)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 98% | 52 | |
| 100% | 100% | 95% | 47 | |
| 100% | 93% | 48% | 23 | |
| 100% | 0% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
One Meraki Wing E (P51800077475)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 2 | |
| 100% | 100% | 100% | 2 | |
| 100% | 100% | 95% | 2 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 6 similar projects in PIN 400071
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 7 mths | 6 yrs 4 mths |
| Possession date extended | Yes | 3 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2024 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | – | 80% |
| MahaRERA complaints (filed by or against the builder) | 0 | 6 |
The 6 projects
- Safal Trademark, Chembur
- Ruparel Orion, Chembur
- Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71, Chembur
- Premiere by Panache, Chembur
- Crystal Armus A to C, Chembur
- Mass Metropolis, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Safal Trademark | August 2017 | April 2027 | 100% | 212 units booked out of 230 units for sale |
| Ruparel Orion | August 2017 | December 2021 | 75% | – |
| Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71 | August 2017 | January 2021 | 100% | 204 units booked out of total 209 units |
| Premiere by Panache | August 2017 | April 2027 | 100% | 138 units booked out of 206 units for sale |
| Crystal Armus A to C | July 2017 | December 2023 | 97% | – |
| Mass Metropolis | September 2017 | December 2025 | 100% | 302 units booked out of 447 units for sale |
About this project
One Meraki by Meraki Habitats LLP is a 291-unit BMC-sanctioned project in Chembur, Mumbai 400071, registered with MahaRERA in 3 phases, with possession due in December 2026. The concrete structure (RCC) is complete.
Read full summary
One Meraki is a BMC-sanctioned project by Meraki Habitats LLP in Chembur, Mumbai 400071, registered with MahaRERA as 3 phases (P51800011606, P51800050796, P51800077475). The first phase was launched in August 2017. Together the phases have 291 units in 4 buildings, with 2, 3 and 5+ BHK homes as registered with MahaRERA. On MahaRERA, 2 are active and 1 is completed.
The registered possession date is December 2026; 1 of 3 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 99% complete. All 3 phases have their structure complete.