Shambhav Darshan, Borivali East
by Aavishkar Enterprises · Borivali East, Mumbai 400066 · Map
- Launched
- Aug 20173 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 6 yrs
- Concrete structure
- 90%Mid-construction
- Booked
- 23 of 2688%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 4Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 1
- 1 BHK
- 13
- 2 BHK
- 6
- Other units
- 6
- Total units
- 26
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 85% | 23 | |
| 100% | 90% | 85% | 23 | |
| 100% | 85% | 0% | 22 | |
| 100% | 85% | 0% | 21 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400066
Projects with 10–40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 4 mths | 4 yrs 4 mths |
| Possession date extended | By 6 yrs | 4 of 4 |
| Possession date (MahaRERA) | Dec 2026 | Jun 2026 |
| Concrete structure (RCC) | 90% | 34% |
| Units booked | 88% | 96% |
| MahaRERA complaints (filed by or against the builder) | 4 | 0 |
The 4 projects
- Sanskriti, Borivali East
- Ekta Appartment From 18th Floor To 22nd Floor, Borivali East
- Mayur Pankh Chs Ltd, Borivali East
- Navkar Heights, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sanskriti | August 2017 | June 2027 | 50% | 24 units booked out of total 25 units |
| Ekta Appartment From 18th Floor To 22nd Floor | August 2017 | December 2026 | 17% | – |
| Mayur Pankh Chs Ltd | August 2017 | December 2025 | 100% | 40 units booked out of total 56 units |
| Navkar Heights | August 2017 | December 2023 | 0% | 35 units booked out of total 36 units |
About this project
Shambhav Darshan by Aavishkar Enterprises is a 26-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in August 2017 with possession due in December 2026. 23 units booked out of total 26 units. The concrete structure (RCC) is 90% complete.
Read full summary
Shambhav Darshan is a BMC-sanctioned project by Aavishkar Enterprises in Borivali East, Mumbai 400066, registered with MahaRERA as P51800009321. It was launched in August 2017. It has 26 units in 1 building: 20 homes (1 RK, 1 BHK and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 6 years from the original December 2020. Construction: excavation complete, structure (RCC) 90% complete, final finishes 85% complete.
23 units booked out of total 26 units (88%).