Mayur Pankh Chs Ltd, Borivali East

Lapsed

by Brightmen Buildspaces LLP · Borivali East, Mumbai 400066 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 3 yrsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
40 of 5671%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
7
2 BHK
27
Other units
22
Total units
56
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services85%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 85%Dec 2025: Final finishes 85%Jul 2026: Final finishes 85%Oct 2026: Final finishes 85%Excavation 100%Concrete structure (RCC) 100%Final finishes 85%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%85%40
100%100%85%–
100%100%85%–
100%100%85%40

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400066

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths3 yrs 5 mths
Possession date extendedBy 3 yrs6 of 6
Possession date (MahaRERA)Dec 2025Sep 2026
Concrete structure (RCC)100%58%
Units booked71%97%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Mayur Pankh Chs Ltd by Brightmen Buildspaces LLP is a 56-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in August 2017; its MahaRERA registration has lapsed. 40 units booked out of total 56 units. The concrete structure (RCC) is complete.

Read full summary

Mayur Pankh Chs Ltd is a BMC-sanctioned project by Brightmen Buildspaces LLP in Borivali East, Mumbai 400066, registered with MahaRERA as P51800005151. It was launched in August 2017. It has 56 units in 1 building: 34 homes (1 and 2 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 3 years from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.

40 units booked out of total 56 units (71%).