Ekta Appartment From 18th Floor To 22nd Floor, Borivali East
by Aditya Enterprise Project Ekta · Borivali East, Mumbai 400066 · Map
- Launched
- Aug 20174 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 5 yrs
- Concrete structure
- 17%Mid-construction
- Booked
- –
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 14
- 3 BHK
- 14
- Total units
- 28
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 17% | 0% | – | |
| 100% | 17% | 0% | – | |
| 100% | 17% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400066
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 4 mths | 3 yrs 10 mths |
| Possession date extended | By 5 yrs | 4 of 4 |
| Possession date (MahaRERA) | Dec 2026 | Jun 2026 |
| Concrete structure (RCC) | 17% | 70% |
| Units booked | – | 92% |
| MahaRERA complaints (filed by or against the builder) | 0 | 1 |
The 4 projects
- Sanskriti, Borivali East
- Mayur Pankh Chs Ltd, Borivali East
- Navkar Heights, Borivali East
- Shambhav Darshan, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sanskriti | August 2017 | June 2027 | 50% | 24 units booked out of total 25 units |
| Mayur Pankh Chs Ltd | August 2017 | December 2025 | 100% | 40 units booked out of total 56 units |
| Navkar Heights | August 2017 | December 2023 | 0% | 35 units booked out of total 36 units |
| Shambhav Darshan | August 2017 | December 2026 | 90% | 23 units booked out of total 26 units |
About this project
Ekta Appartment From 18th Floor To 22nd Floor by Aditya Enterprise Project Ekta is a 28-unit MHADA-sanctioned project in Borivali East, Mumbai 400066, launched in August 2017 with possession due in December 2026. The concrete structure (RCC) is 17% complete.
Read full summary
Ekta Appartment From 18th Floor To 22nd Floor is a MHADA-sanctioned project by Aditya Enterprise Project Ekta in Borivali East, Mumbai 400066, registered with MahaRERA as P51800011046. It was launched in August 2017. It has 28 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 5 years from the original December 2021. Construction: excavation complete, structure (RCC) 17% complete, final finishes not started.