Sanskriti, Borivali East

by Jem And Associates · Borivali East, Mumbai 400066 · Map

Launched
Aug 20173 yrs 5 mths originally promised
Possession (MahaRERA)
Jun 2027Extended by 6 yrs 5 mths
Concrete structure
50%Mid-construction
Booked
24 of 2596%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
21
3 BHK
3
5+ BHK
1
Total units
25
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)50%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 50%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 50%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%0%24
100%50%0%24
100%100%0%–
100%100%0%7

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400066

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 5 mths4 yrs 4 mths
Possession date extendedBy 6 yrs 5 mths4 of 4
Possession date (MahaRERA)Jun 2027Jun 2026
Concrete structure (RCC)50%54%
Units booked96%88%
MahaRERA complaints (filed by or against the builder)01

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Sanskriti by Jem And Associates is a 25-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in August 2017 with possession due in June 2027. 24 units booked out of total 25 units. The concrete structure (RCC) is 50% complete.

Read full summary

Sanskriti is a BMC-sanctioned project by Jem And Associates in Borivali East, Mumbai 400066, registered with MahaRERA as P51800011430. It was launched in August 2017. It has 25 units in 1 building, with 1, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, extended by 6 years 5 months from the original January 2021. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.

24 units booked out of total 25 units (96%).