Royal Accord, Dahisar

by Viva Homes Private Limited · Dahisar, Mumbai 400068 · Map

Launched
Aug 20174 yrs 4 mths originally promised
Possession (MahaRERA)
Jun 2027Extended by 5 yrs 6 mths
Concrete structure
67%Mid-construction
Booked (free sale)
29 of 4663%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale29 booked out of 46 units

Land-owner share7 units, not for sale

Total 53 units. Land-owner units are not for sale.

Project facts

1 BHK
23
2 BHK
22
Other units
8
Total units
53
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
46
Land-owner share (not for sale)
7

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)67%
Finishes, lifts and services35%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 67%Jul 2026: Concrete structure (RCC) 67%Oct 2026: Concrete structure (RCC) 67%Dec 2024: Final finishes 35%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 35%Excavation 100%Concrete structure (RCC) 67%Final finishes 35%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%67%35%29
100%67%0%29
100%67%0%29
100%60%35%28

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400068

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths2 yrs 4 mths
Possession date extendedBy 5 yrs 6 mths6 of 6
Possession date (MahaRERA)Jun 2027Sep 2026
Concrete structure (RCC)67%82%
Units booked (free sale)63%49%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Royal Accord by Viva Homes Private Limited is a 53-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in August 2017 with possession due in June 2027. 29 units booked out of 46 units for sale. The concrete structure (RCC) is 67% complete.

Read full summary

Royal Accord is a BMC-sanctioned project by Viva Homes Private Limited in Dahisar, Mumbai 400068, registered with MahaRERA as P51800010302. It was launched in August 2017. It has 53 units in 1 building: 45 homes (1 and 2 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 53 units, 46 are for sale and 7 are the land-owner's share, not for sale.

Its registered possession date is June 2027, extended by 5 years 6 months from the original December 2021. Construction: excavation complete, structure (RCC) 67% complete, final finishes 35% complete.

29 units booked out of 46 units for sale (63%).