Skip to main content

Yashwant Height, Dahisar

by M.P. Global Height Private Limited · Dahisar, Mumbai 400068 · Map

Launched
Aug 20174 yrs 4 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 5 yrs 4 mths
Concrete structure
70%Mid-construction
Booked
38 of 7749%
Buildings
10.4 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
20
2 BHK
19
3 BHK
19
Other units
19
Total units
77
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 40%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 70%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 70%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%0%38
100%70%0%–
100%70%0%–
100%40%0%38

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400068

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths2 yrs 4 mths
Possession date extendedBy 5 yrs 4 mths6 of 6
Possession date (MahaRERA)Apr 2027Mar 2026
Concrete structure (RCC)70%90%
Units booked49%62%
MahaRERA complaints (filed by or against the builder)30

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Yashwant Height by M.P. Global Height Private Limited is a 77-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in August 2017 with possession due in April 2027. 38 units booked out of total 77 units. The concrete structure (RCC) is 70% complete.

Read full summary

Yashwant Height is a BMC-sanctioned project by M.P. Global Height Private Limited in Dahisar, Mumbai 400068, registered with MahaRERA as P51800010825. It was launched in August 2017. It has 77 units in 1 building: 58 homes (1, 2 and 3 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2027, extended by 5 years 4 months from the original December 2021. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.

38 units booked out of total 77 units (49%).