Kshitij Heights, Dahisar
by M/s Kishore Metal & Wire Industries · Dahisar, Mumbai 400068 · Map
- Launched
- Aug 20177 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2029Extended by 5 yrs
- Concrete structure
- 45%Mid-construction
- Booked
- 4 of 904%
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 18
- 2 BHK
- 66
- Other units
- 6
- Total units
- 90
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 45% | 20% | 4 | |
| 100% | 45% | 20% | – | |
| 100% | 45% | 20% | – | |
| 100% | 45% | 20% | 4 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400068
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 4 mths | 2 yrs 2 mths |
| Possession date extended | By 5 yrs | 6 of 6 |
| Possession date (MahaRERA) | Dec 2029 | Jun 2026 |
| Concrete structure (RCC) | 45% | 92% |
| Units booked | 4% | 90% |
| MahaRERA complaints (filed by or against the builder) | 0 | 2 |
The 6 projects
- Haritara Residency / Haritara Co-operative Housing Society Limited, Dahisar
- Om Shiv Matoshree SRA CHS LTD, Dahisar
- Shri Sai Vishram CHSL, Dahisar
- Vklal Vishnu Phase I, Dahisar
- Royal Accord, Dahisar
- Vishwakarma Nagar Chsl-Phase 2, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Haritara Residency / Haritara Co-operative Housing Society Limited | August 2017 | April 2020 | 100% | – |
| Om Shiv Matoshree SRA CHS LTD | August 2017 | December 2026 | 100% | 272 units booked out of total 313 units |
| Shri Sai Vishram CHSL | August 2017 | December 2025 | 85% | – |
| Vklal Vishnu Phase I | August 2017 | December 2026 | 100% | 62 units booked out of total 66 units |
| Royal Accord | August 2017 | June 2027 | 67% | 29 units booked out of 46 units for sale |
| Vishwakarma Nagar Chsl-Phase 2 | November 2017 | December 2022 | 46% | 50 units booked out of total 53 units |
About this project
Kshitij Heights by M/s Kishore Metal & Wire Industries is a 90-unit project in Dahisar, Mumbai 400068, launched in August 2017 with possession due in December 2029. 4 units booked out of total 90 units. The concrete structure (RCC) is 45% complete.
Read full summary
Kshitij Heights is a project by M/s Kishore Metal & Wire Industries in Dahisar, Mumbai 400068, registered with MahaRERA as P51800008811. It was launched in August 2017. It has 90 units in 1 building: 84 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, extended by 5 years from the original December 2024. Construction: excavation complete, structure (RCC) 45% complete, final finishes 20% complete.
4 units booked out of total 90 units (4%).