Vklal Vishnu Phase I, Dahisar

Ready to move

by Veekaylal Investment Company Private Limited · Dahisar, Mumbai 400068 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 3 yrs
Concrete structure
100%Ready to move
Booked
62 of 6694%
Buildings
10.5 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
66
Total units
66
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 75%Dec 2025: Final finishes 85%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%62
100%100%100%62
100%100%85%62
100%100%75%56

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400068

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 4 mths2 yrs 4 mths
Possession date extendedBy 3 yrs6 of 6
Possession date (MahaRERA)Dec 2026Jun 2026
Concrete structure (RCC)100%90%
Units booked94%55%
MahaRERA complaints (filed by or against the builder)42

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Vklal Vishnu Phase I by Veekaylal Investment Company Private Limited is a 66-unit SRA-sanctioned project in Dahisar, Mumbai 400068, launched in August 2017 with possession due in December 2026. 62 units booked out of total 66 units. The concrete structure (RCC) is complete.

Read full summary

Vklal Vishnu Phase I is an SRA-sanctioned project by Veekaylal Investment Company Private Limited in Dahisar, Mumbai 400068, registered with MahaRERA as P51800011626. It was launched in August 2017. It has 66 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 3 years from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

62 units booked out of total 66 units (94%).