Shri Sai Vishram CHSL, Dahisar

Lapsed

by Aaryadeep Builders & Developers · Dahisar, Mumbai 400068 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 6 yrsWhat does Lapsed mean?
Concrete structure
85%Mid-construction
Booked
–
Buildings
10.6 acres
MahaRERA complaints
8Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
27
2 BHK
21
3 BHK
21
Other units
3
Total units
72
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 85%Dec 2025: Concrete structure (RCC) 85%Jul 2026: Concrete structure (RCC) 85%Oct 2026: Concrete structure (RCC) 85%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 85%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%80%118
100%85%80%–
100%85%80%–
100%85%80%118

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400068

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths3 yrs 4 mths
Possession date extendedBy 6 yrs6 of 6
Possession date (MahaRERA)Dec 2025Dec 2026
Concrete structure (RCC)85%98%
Units booked–60%
MahaRERA complaints (filed by or against the builder)82

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shri Sai Vishram CHSL by Aaryadeep Builders & Developers is a 72-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 85% complete.

Read full summary

Shri Sai Vishram CHSL is a BMC-sanctioned project by Aaryadeep Builders & Developers in Dahisar, Mumbai 400068, registered with MahaRERA as P51700006499. It was launched in August 2017. It has 72 units in 1 building: 69 homes (1, 2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 6 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 85% complete, final finishes 80% complete.

Since the July 2026 update, the possession date has moved from December 2022 to December 2025.