Vishwakarma Nagar Chsl-Phase 2, Dahisar

Lapsed

by Ssakash Developers & Builders · Dahisar, Mumbai 400068 · Map

Launched
Nov 20172 yrs 1 mth originally promised
Possession (MahaRERA)
Dec 2022Extended by 3 yrsWhat does Lapsed mean?
Concrete structure
46%Mid-construction
Booked
50 of 5394%
Buildings
20.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
39
3 BHK
3
Other units
11
Total units
53
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)46%
Finishes, lifts and services46%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Oct 2026: Excavation 50%Dec 2024: Concrete structure (RCC) 46%Dec 2025: Concrete structure (RCC) 46%Jul 2026: Concrete structure (RCC) 46%Oct 2026: Concrete structure (RCC) 46%Dec 2024: Final finishes 46%Dec 2025: Final finishes 46%Jul 2026: Final finishes 46%Oct 2026: Final finishes 46%Excavation 50%Concrete structure (RCC) 46%Final finishes 46%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%46%46%50
50%46%46%–
50%46%46%–
50%46%46%50

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400068

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 1 mth2 yrs 1 mth
Possession date extendedBy 3 yrs4 of 4
Possession date (MahaRERA)Dec 2022Sep 2026
Concrete structure (RCC)46%72%
Units booked94%38%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Vishwakarma Nagar Chsl-Phase 2 by Ssakash Developers & Builders is a 53-unit project in Dahisar, Mumbai 400068, launched in November 2017; its MahaRERA registration has lapsed. 50 units booked out of total 53 units. The concrete structure (RCC) is 46% complete.

Read full summary

Vishwakarma Nagar Chsl-Phase 2 is a project by Ssakash Developers & Builders in Dahisar, Mumbai 400068, registered with MahaRERA as P51800014214. It was launched in November 2017. It has 53 units in 2 buildings: 42 homes (2 and 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2022, after an extension of 3 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation 50% complete, structure (RCC) 46% complete, final finishes 46% complete.

50 units booked out of total 53 units (94%).