Vishwakarma Nagar Chsl-Phase 2, Dahisar
Lapsed
by Ssakash Developers & Builders · Dahisar, Mumbai 400068 · Map
- Launched
- Nov 20172 yrs 1 mth originally promised
- Possession (MahaRERA)
- Dec 2022Extended by 3 yrsWhat does Lapsed mean?
- Concrete structure
- 46%Mid-construction
- Booked
- 50 of 5394%
- Buildings
- 20.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 39
- 3 BHK
- 3
- Other units
- 11
- Total units
- 53
- Buildings
- 2
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 46% | 46% | 50 | |
| 50% | 46% | 46% | – | |
| 50% | 46% | 46% | – | |
| 50% | 46% | 46% | 50 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400068
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 1 mth | 2 yrs 1 mth |
| Possession date extended | By 3 yrs | 4 of 4 |
| Possession date (MahaRERA) | Dec 2022 | Sep 2026 |
| Concrete structure (RCC) | 46% | 72% |
| Units booked | 94% | 38% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Ashoka Co-Op Hsg Society Limited, Dahisar
- Kshitij Heights, Dahisar
- Om Shiv Matoshree SRA CHS LTD, Dahisar
- Dahisar Manisha Chs Ltd, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ashoka Co-Op Hsg Society Limited | August 2017 | July 2026 | 35% | 12 units booked out of 32 units for sale |
| Kshitij Heights | August 2017 | December 2029 | 45% | 4 units booked out of total 90 units |
| Om Shiv Matoshree SRA CHS LTD | August 2017 | December 2026 | 100% | 272 units booked out of total 313 units |
| Dahisar Manisha Chs Ltd | July 2017 | March 2024 | 100% | – |
About this project
Vishwakarma Nagar Chsl-Phase 2 by Ssakash Developers & Builders is a 53-unit project in Dahisar, Mumbai 400068, launched in November 2017; its MahaRERA registration has lapsed. 50 units booked out of total 53 units. The concrete structure (RCC) is 46% complete.
Read full summary
Vishwakarma Nagar Chsl-Phase 2 is a project by Ssakash Developers & Builders in Dahisar, Mumbai 400068, registered with MahaRERA as P51800014214. It was launched in November 2017. It has 53 units in 2 buildings: 42 homes (2 and 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2022, after an extension of 3 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation 50% complete, structure (RCC) 46% complete, final finishes 46% complete.
50 units booked out of total 53 units (94%).