Vrindavan, Malad East

Lapsed

by Je And Vee Infrastructure · Malad East, Mumbai 400097 · Map

Launched
Jul 20186 yrs 5 mths promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
23%Mid-construction
Booked
–
Buildings
10.2 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
40
2 BHK
38
Other units
3
Total units
81
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)23%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 23%Dec 2025: Concrete structure (RCC) 23%Jul 2026: Concrete structure (RCC) 23%Dec 2024: Final finishes 60%Dec 2025: Final finishes 60%Jul 2026: Final finishes 60%Excavation 100%Final finishes 60%Concrete structure (RCC) 23%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%23%60%–
100%23%60%–
100%23%60%78

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400097

Projects with 30–200 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 5 mths5 yrs 11 mths
Possession date extendedNo3 of 3
Possession date (MahaRERA)Dec 2024Mar 2028
Concrete structure (RCC)23%13%
Units booked–56%
MahaRERA complaints (filed by or against the builder)26

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Vrindavan by Je And Vee Infrastructure is an 81-unit project in Malad East, Mumbai 400097, launched in July 2018; its MahaRERA registration has lapsed. The concrete structure (RCC) is 23% complete.

Read full summary

Vrindavan is a project by Je And Vee Infrastructure in Malad East, Mumbai 400097, registered with MahaRERA as P51800017298. It was launched in July 2018. It has 81 units in 1 building: 78 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 23% complete, final finishes 60% complete.