Sheth Blue Ivy, Malad East

by Sheth Developers Private Limited · Malad East, Mumbai 400097 · Map

Launched
Jul 20175 yrs 11 mths originally promised
Possession (MahaRERA)
Mar 2028Extended by 4 yrs 9 mths
Concrete structure
3%Mid-construction
Booked
37 of 6656%
Buildings
10.4 acres
MahaRERA complaints
19Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
4
3 BHK
1
4 BHK
61
Total units
66
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
19

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)3%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 3%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 3%Dec 2024: Final finishes 10%Dec 2025: Final finishes 10%Jul 2026: Final finishes 10%Oct 2026: Final finishes 10%Excavation 100%Final finishes 10%Concrete structure (RCC) 3%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%3%10%37
100%0%10%37
100%0%10%37
100%3%10%37

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400097

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 11 mths5 yrs 11 mths
Possession date extendedBy 4 yrs 9 mths4 of 6
Possession date (MahaRERA)Mar 2028Sep 2025
Concrete structure (RCC)3%95%
Units booked56%72%
MahaRERA complaints (filed by or against the builder)192

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Sheth Blue Ivy by Sheth Developers Private Limited is a 66-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in July 2017 with possession due in March 2028. 37 units booked out of total 66 units. The concrete structure (RCC) is 3% complete.

Read full summary

Sheth Blue Ivy is a BMC-sanctioned project by Sheth Developers Private Limited in Malad East, Mumbai 400097, registered with MahaRERA as P51800001407. It was launched in July 2017. It has 66 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2028, extended by 4 years 9 months from the original June 2023. Construction: excavation complete, structure (RCC) 3% complete, final finishes 10% complete.

37 units booked out of total 66 units (56%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 3% and the possession date has moved from June 2024 to March 2028.