Nirlon Employees Chs Ltd Building No. 10, Goregaon West
by Shivam Parivar Developers Private Limited · Goregaon West, Mumbai 400062 · Map
- Launched
- Apr 20213 yrs 2 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 2 yrs 10 mths
- Concrete structure
- 72%Mid-construction
- Booked (free sale)
- 81 of 9090% · 33 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale81 booked out of 90 units
Rehab33 units for existing members
Total 123 units. Rehab units are not for sale.
Project facts
- 1 RK
- 3
- 1 BHK
- 6
- 2 BHK
- 100
- Other units
- 14
- Total units
- 123
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 90
- Rehab units
- 33
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 72% | 2% | 81 | |
| 100% | 72% | 2% | 81 | |
| 100% | 72% | 2% | 82 | |
| 100% | 72% | 2% | 43 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400062
Projects with 50–250 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 2 mths | 3 yrs 10 mths |
| Possession date extended | By 2 yrs 10 mths | 3 of 3 |
| Possession date (MahaRERA) | Apr 2027 | Apr 2027 |
| Concrete structure (RCC) | 72% | 43% |
| Units booked (free sale) | 90% | 60% |
| MahaRERA complaints (filed by or against the builder) | 2 | 0 |
The 3 projects
- Krishna Kunj Phase 1, Goregaon West
- Agarwal Florence, Goregaon West
- Gundecha Rexon Suites Phase 1, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Krishna Kunj Phase 1 | February 2022 | March 2027 | 43% | 84 units booked out of 91 units for sale |
| Agarwal Florence | February 2022 | April 2027 | 100% | 88 units booked out of total 146 units |
| Gundecha Rexon Suites Phase 1 | April 2022 | October 2028 | 27% | 25 units booked out of 123 units for sale |
About this project
Nirlon Employees Chs Ltd Building No. 10 by Shivam Parivar Developers Private Limited is a 123-unit MHADA-sanctioned project in Goregaon West, Mumbai 400062, launched in April 2021 with possession due in April 2027. 81 units booked out of 90 units for sale. The concrete structure (RCC) is 72% complete.
Read full summary
Nirlon Employees Chs Ltd Building No. 10 is a MHADA-sanctioned project by Shivam Parivar Developers Private Limited in Goregaon West, Mumbai 400062, registered with MahaRERA as P51800029048. It was launched in April 2021. It has 123 units in 1 building: 109 homes (1 RK, 1 BHK and 2 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 123 units, 90 are for sale and 33 are rehab units for existing members.
Its registered possession date is April 2027, extended by 2 years 10 months from the original June 2024. Construction: excavation complete, structure (RCC) 72% complete, final finishes 2% complete.
81 units booked out of 90 units for sale (90%).