Agarwal Florence, Goregaon West

Ready to move

by Param Anand Builders LLP · Goregaon West, Mumbai 400062 · Map

Launched
Feb 20223 yrs 10 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 1 yr 4 mths
Concrete structure
100%Ready to move
Booked
88 of 14660% · 80 in Jul 2026
Buildings
11 acre
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
24
2 BHK
51
3 BHK
56
5+ BHK
15
Total units
146
Buildings
1
Land
1 acre
Phases
1
MahaRERA complaints
1
Reserved units
24

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 75%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%88
100%100%75%80
100%100%0%53
100%100%0%48

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400062

Projects with 70–300 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400062
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths3 yrs 2 mths
Possession date extendedBy 1 yr 4 mths3 of 3
Possession date (MahaRERA)Apr 2027Apr 2027
Concrete structure (RCC)100%43%
Units booked60%90%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Agarwal Florence by Param Anand Builders LLP is a 146-unit BMC-sanctioned project in Goregaon West, Mumbai 400062, launched in February 2022 with possession due in April 2027. 88 units booked out of total 146 units. The concrete structure (RCC) is complete.

Read full summary

Agarwal Florence is a BMC-sanctioned project by Param Anand Builders LLP in Goregaon West, Mumbai 400062, registered with MahaRERA as P51800032916. It was launched in February 2022. It has 146 units in 1 building, with 1 RK, 2 BHK, 3 BHK and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2027, extended by 1 year 4 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

88 units booked out of total 146 units (60%). Since the July 2026 update, 8 more units have been booked and the possession date has moved from June 2026 to April 2027.