Krishna Kunj Phase 1, Goregaon West

by Prince Housing And Hospitality Private Limited · Goregaon West, Mumbai 400062 · Map

Launched
Feb 20222 yrs 11 mths originally promised
Possession (MahaRERA)
Mar 2027Extended by 2 yrs 2 mths
Concrete structure
43%Mid-construction
Booked (free sale)
84 of 9192% · 46 rehab units
Buildings
30.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale84 booked out of 91 units

Rehab46 units for existing members

Total 137 units. Rehab units are not for sale.

Project facts

1 BHK
65
2 BHK
39
3 BHK
3
Other units
30
Total units
137
Buildings
3
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
91
Rehab units
46
Reserved units
35

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)43%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 67%Jul 2026: Excavation 67%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 43%Dec 2025: Concrete structure (RCC) 28%Jul 2026: Concrete structure (RCC) 28%Oct 2026: Concrete structure (RCC) 43%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 43%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%43%0%84
67%28%0%87
67%28%0%90
100%43%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400062

Projects with 50–250 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400062
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 11 mths3 yrs 10 mths
Possession date extendedBy 2 yrs 2 mths3 of 3
Possession date (MahaRERA)Mar 2027Apr 2027
Concrete structure (RCC)43%72%
Units booked (free sale)92%60%
MahaRERA complaints (filed by or against the builder)01

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Krishna Kunj Phase 1 by Prince Housing And Hospitality Private Limited is a 137-unit BMC-sanctioned project in Goregaon West, Mumbai 400062, launched in February 2022 with possession due in March 2027. 84 units booked out of 91 units for sale. The concrete structure (RCC) is 43% complete.

Read full summary

Krishna Kunj Phase 1 is a BMC-sanctioned project by Prince Housing And Hospitality Private Limited in Goregaon West, Mumbai 400062, registered with MahaRERA as P51800033187. It was launched in February 2022. It has 137 units in 3 buildings: 107 homes (1, 2 and 3 BHK) and 30 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 137 units, 91 are for sale and 46 are rehab units for existing members.

Its registered possession date is March 2027, extended by 2 years 2 months from the original January 2025. Construction: excavation complete, structure (RCC) 43% complete, final finishes not started.

84 units booked out of 91 units for sale (92%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 28% to 43% and the possession date has moved from January 2026 to March 2027.