Gundecha Rexon Suites Phase 1, Goregaon West

by Anaya Infrastructure Pvt Ltd · Goregaon West, Mumbai 400062 · Map

Launched
Apr 20223 yrs 11 mths originally promised
Possession (MahaRERA)
Oct 2028Extended by 2 yrs 7 mths
Concrete structure
27%Mid-construction
Booked (free sale)
25 of 12320% · 96 rehab units
Buildings
11.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale25 booked out of 123 units

Rehab96 units for existing members

Land-owner share11 units, not for sale

Total 230 units. Rehab and land-owner units are not for sale.

Project facts

2 BHK
60
3 BHK
140
4 BHK
30
Total units
230
Buildings
1
Land
1.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
123
Rehab units
96
Land-owner share (not for sale)
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)27%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 27%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 27%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%27%0%25
100%0%0%–
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400062

Projects with 100–500 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400062
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths3 yrs 2 mths
Possession date extendedBy 2 yrs 7 mths3 of 3
Possession date (MahaRERA)Oct 2028Apr 2027
Concrete structure (RCC)27%72%
Units booked (free sale)20%90%
MahaRERA complaints (filed by or against the builder)01

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Gundecha Rexon Suites Phase 1 by Anaya Infrastructure Pvt Ltd is a 230-unit SRA-sanctioned project in Goregaon West, Mumbai 400062, launched in April 2022 with possession due in October 2028. 25 units booked out of 123 units for sale. The concrete structure (RCC) is 27% complete.

Read full summary

Gundecha Rexon Suites Phase 1 is an SRA-sanctioned project by Anaya Infrastructure Pvt Ltd in Goregaon West, Mumbai 400062, registered with MahaRERA as P51800034503. It was launched in April 2022. It has 230 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 230 units, 123 are for sale, 96 are rehab units for existing members and 11 are the land-owner's share, not for sale.

Its registered possession date is October 2028, extended by 2 years 7 months from the original March 2026. Construction: excavation complete, structure (RCC) 27% complete, final finishes not started.

25 units booked out of 123 units for sale (20%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 27%.