Gauri Excellency Nx, Kandivali West

Lapsed

by M/S Gauri Land Developers LLP · Kandivali West, Mumbai 400067 · Map

Launched
Jul 20212 yrs 5 mths originally promised
Possession (MahaRERA)
Jun 2026Extended by 2 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
18%Mid-construction
Booked
183 of 18897%
Buildings
13 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
64
2 BHK
124
Total units
188
Buildings
1
Land
3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)18%
Finishes, lifts and services93%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 18%Jul 2026: Concrete structure (RCC) 18%Oct 2026: Concrete structure (RCC) 18%Dec 2024: Final finishes 75%Dec 2025: Final finishes 90%Jul 2026: Final finishes 93%Oct 2026: Final finishes 93%Excavation 100%Final finishes 93%Concrete structure (RCC) 18%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%18%93%183
100%18%93%183
100%18%90%181
100%0%75%168

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400067

Projects with 90–400 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths4 yrs 7 mths
Possession date extendedBy 2 yrs 6 mths3 of 5
Possession date (MahaRERA)Jun 2026Mar 2027
Concrete structure (RCC)18%100%
Units booked97%85%
MahaRERA complaints (filed by or against the builder)10

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Gauri Excellency Nx by M/S Gauri Land Developers LLP is a 188-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in July 2021; its MahaRERA registration has lapsed. 183 units booked out of total 188 units. The concrete structure (RCC) is 18% complete.

Read full summary

Gauri Excellency Nx is an SRA-sanctioned project by M/S Gauri Land Developers LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800029939. It was launched in July 2021. It has 188 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026, after an extension of 2 years 6 months from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 18% complete, final finishes 93% complete.

183 units booked out of total 188 units (97%).