Shreeji Sky Rise Tower, Kandivali West

by Shreeji Construction · Kandivali West, Mumbai 400067 · Map

Launched
Dec 20215 yrs promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked
206 of 23787% · 204 in Jul 2026
Buildings
11.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
102
3 BHK
80
Other units
55
Total units
237
Buildings
1
Land
1.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services58%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 45%Dec 2025: Concrete structure (RCC) 82%Jul 2026: Concrete structure (RCC) 92%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 30%Jul 2026: Final finishes 58%Oct 2026: Final finishes 58%Excavation 100%Concrete structure (RCC) 100%Final finishes 58%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%58%206
100%92%58%204
100%82%30%206
100%45%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400067

Projects with 90–400 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs4 yrs 1 mth
Possession date extendedNo4 of 5
Possession date (MahaRERA)Dec 2026Mar 2027
Concrete structure (RCC)100%100%
Units booked87%84%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Shreeji Sky Rise Tower by Shreeji Construction is a 237-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in December 2021 with possession due in December 2026. 206 units booked out of total 237 units. The concrete structure (RCC) is complete.

Read full summary

Shreeji Sky Rise Tower is an SRA-sanctioned project by Shreeji Construction in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800032149. It was launched in December 2021. It has 237 units in 1 building: 182 homes (2 and 3 BHK) and 55 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 58% complete.

206 units booked out of total 237 units (87%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 92% to 100%.