Asmi Legend, Goregaon West
by Angel Construction Company · Goregaon West, Mumbai 400104 · Map
- Launched
- Dec 20213 yrs originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 3 yrs
- Concrete structure
- 97%Mid-construction
- Booked
- 106 of 16863% · 99 in Jul 2026
- Buildings
- 30.8 acres
- MahaRERA complaints
- 4Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 70
- 2 BHK
- 92
- Other units
- 6
- Total units
- 168
- Buildings
- 3
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 97% | 43% | 106 | |
| 100% | 97% | 43% | 99 | |
| 100% | 92% | 43% | 94 | |
| 100% | 92% | 30% | 86 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400104
Projects with 80–350 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs | 4 yrs |
| Possession date extended | By 3 yrs | 3 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Jul 2026 |
| Concrete structure (RCC) | 97% | 84% |
| Units booked | 63% | 63% |
| MahaRERA complaints (filed by or against the builder) | 4 | 0 |
The 6 projects
- 36 Allure, Goregaon West
- Ghodawat Skystar LLP, Goregaon West
- Goregaon Vihar Darshan Chs Ltd, Goregaon West
- Asmi Legacy, Goregaon West
- Sejal Kajal Apartment Chs Ltd, Goregaon West
- Shastri Nagar Prerna C.H.S.Ltd, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| 36 Allure | December 2021 | June 2025 | 67% | 86 units booked out of total 124 units |
| Ghodawat Skystar LLP | December 2021 | June 2026 | 100% | 39 units booked out of total 84 units |
| Goregaon Vihar Darshan Chs Ltd | January 2022 | August 2026 | 100% | 70 units booked out of total 85 units |
| Asmi Legacy | November 2021 | December 2026 | 51% | 70 units booked out of 190 units for sale |
| Sejal Kajal Apartment Chs Ltd | August 2022 | July 2026 | 33% | 91 units booked out of 139 units for sale |
| Shastri Nagar Prerna C.H.S.Ltd | January 2021 | October 2027 | 100% | 64 units booked out of 106 units for sale |
About this project
Asmi Legend by Angel Construction Company is a 168-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, launched in December 2021 with possession due in December 2027. 106 units booked out of total 168 units. The concrete structure (RCC) is 97% complete.
Read full summary
Asmi Legend is a BMC-sanctioned project by Angel Construction Company in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800032085. It was launched in December 2021. It has 168 units in 3 buildings: 162 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 3 years from the original December 2024. Construction: excavation complete, structure (RCC) 97% complete, final finishes 43% complete.
106 units booked out of total 168 units (63%). Since the July 2026 update, 7 more units have been booked and the possession date has moved from December 2025 to December 2027.