- Launched
- Dec 20213 yrs 6 mths promised
- Possession (MahaRERA)
- Jun 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 67%Mid-construction
- Booked
- 86 of 12469%
- Buildings
- 10.7 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 43
- 2 BHK
- 77
- Other units
- 4
- Total units
- 124
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 67% | 25% | 86 | |
| 100% | 67% | 25% | – | |
| 100% | 67% | 25% | – | |
| 100% | 67% | 25% | 86 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400104
Projects with 60–250 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 6 mths | 3 yrs 6 mths |
| Possession date extended | No | 4 of 4 |
| Possession date (MahaRERA) | Jun 2025 | Mar 2027 |
| Concrete structure (RCC) | 67% | 100% |
| Units booked | 69% | 62% |
| MahaRERA complaints (filed by or against the builder) | 2 | 0 |
The 4 projects
- Ghodawat Skystar LLP, Goregaon West
- Asmi Legend, Goregaon West
- Goregaon Vihar Darshan Chs Ltd, Goregaon West
- Shastri Nagar Prerna C.H.S.Ltd, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ghodawat Skystar LLP | December 2021 | June 2026 | 100% | 39 units booked out of total 84 units |
| Asmi Legend | December 2021 | December 2027 | 97% | 106 units booked out of total 168 units |
| Goregaon Vihar Darshan Chs Ltd | January 2022 | August 2026 | 100% | 70 units booked out of total 85 units |
| Shastri Nagar Prerna C.H.S.Ltd | January 2021 | October 2027 | 100% | 64 units booked out of 106 units for sale |
About this project
36 Allure by Acme Metal Industries Pvt Ltd is a 124-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, launched in December 2021; its MahaRERA registration has lapsed. 86 units booked out of total 124 units. The concrete structure (RCC) is 67% complete.
Read full summary
36 Allure is a BMC-sanctioned project by Acme Metal Industries Pvt Ltd in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800032348. It was launched in December 2021. It has 124 units in 1 building: 120 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 67% complete, final finishes 25% complete.
86 units booked out of total 124 units (69%).