Splendora, Dadar West

by Shree Varad Constructions · Dadar West, Mumbai 400028 · Map

Launched
Feb 20223 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Nearing possession
Booked (free sale)
26 of 3967% · 27 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale26 booked out of 39 units

Rehab27 units for existing members

Total 66 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
32
2 BHK
16
Other units
17
Total units
66
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
39
Rehab units
27

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%26
100%100%0%26
100%80%0%–
100%80%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400028

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths4 yrs 6 mths
Possession date extendedBy 1 yr2 of 5
Possession date (MahaRERA)Dec 2026Sep 2026
Concrete structure (RCC)100%100%
Units booked (free sale)67%53%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Splendora by Shree Varad Constructions is a 66-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in February 2022 with possession due in December 2026. 26 units booked out of 39 units for sale. The concrete structure (RCC) is complete.

Read full summary

Splendora is a BMC-sanctioned project by Shree Varad Constructions in Dadar West, Mumbai 400028, registered with MahaRERA as P51800033125. It was launched in February 2022. It has 66 units in 1 building: 49 homes (1 RK, 1 BHK and 2 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 66 units, 39 are for sale and 27 are rehab units for existing members.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes not started.

26 units booked out of 39 units for sale (67%).