1891 Ekam Parkk, Dadar West

Ready to move

by Nascent Developers · Dadar West, Mumbai 400028 · Map

Launched
Jun 20224 yrs 6 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Ready to move
Booked (free sale)
18 of 3453% · 6 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale18 booked out of 34 units

Rehab6 units for existing members

Total 40 units. Rehab units are not for sale.

Project facts

1 BHK
18
2 BHK
22
Total units
40
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
34
Rehab units
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 75%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%18
100%100%100%18
100%75%0%18
100%75%0%16

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400028

Projects with 20–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 6 mths3 yrs 9 mths
Possession date extendedNo5 of 6
Possession date (MahaRERA)Dec 2026Feb 2027
Concrete structure (RCC)100%85%
Units booked (free sale)53%54%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

1891 Ekam Parkk by Nascent Developers is a 40-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in June 2022 with possession due in December 2026. 18 units booked out of 34 units for sale. The concrete structure (RCC) is complete.

Read full summary

1891 Ekam Parkk is a BMC-sanctioned project by Nascent Developers in Dadar West, Mumbai 400028, registered with MahaRERA as P51900046004. It was launched in June 2022. It has 40 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 40 units, 34 are for sale and 6 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

18 units booked out of 34 units for sale (53%).