by Mehta Developers · Dadar West, Mumbai 400028 · Map

Launched
Oct 20214 yrs 11 mths promised
Possession (MahaRERA)
Sep 2026Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
16 of 3348%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale16 booked out of 33 units

Land-owner share44 units, not for sale

Total 77 units. Land-owner units are not for sale.

Project facts

1 BHK
36
2 BHK
29
3 BHK
10
Other units
2
Total units
77
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
33
Land-owner share (not for sale)
44

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 98%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%16
100%100%80%15
100%100%0%11
100%98%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400028

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 11 mths3 yrs 5 mths
Possession date extendedNo6 of 6
Possession date (MahaRERA)Sep 2026Dec 2026
Concrete structure (RCC)100%95%
Units booked (free sale)48%67%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Arihant Tower by Mehta Developers is a 77-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in October 2021 with possession due in September 2026. 16 units booked out of 33 units for sale. The concrete structure (RCC) is complete.

Read full summary

Arihant Tower is a BMC-sanctioned project by Mehta Developers in Dadar West, Mumbai 400028, registered with MahaRERA as P51900031107. It was launched in October 2021. It has 77 units in 1 building: 75 homes (1, 2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 77 units, 33 are for sale and 44 are the land-owner's share, not for sale.

Possession was due in September 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

16 units booked out of 33 units for sale (48%). Since the July 2026 update, 1 more unit has been booked.