Park Grandeur, Juhu

Ready to move

by Shree Suraj Resources Private Limited · Juhu, Mumbai 400049 · Map

Launched
May 20227 yrs 7 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
100%Ready to move
Booked (free sale)
39 of 5374% · 20 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale39 booked out of 53 units

Rehab20 units for existing members

Total 73 units. Rehab units are not for sale.

Project facts

3 BHK
67
4 BHK
6
Total units
73
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
53
Rehab units
20

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 40%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%39
100%100%100%39
100%100%40%30
100%90%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400049

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400049
MeasureThis projectSimilar projects
Launch to possession (as first promised)7 yrs 7 mths4 yrs 3 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)Dec 2029Dec 2026
Concrete structure (RCC)100%85%
Units booked (free sale)74%44%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Park Grandeur by Shree Suraj Resources Private Limited is a 73-unit MHADA-sanctioned project in Juhu, Mumbai 400049, launched in May 2022 with possession due in December 2029. 39 units booked out of 53 units for sale. The concrete structure (RCC) is complete.

Read full summary

Park Grandeur is a MHADA-sanctioned project by Shree Suraj Resources Private Limited in Juhu, Mumbai 400049, registered with MahaRERA as P51800045369. It was launched in May 2022. It has 73 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 73 units, 53 are for sale and 20 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

39 units booked out of 53 units for sale (74%).