Elenora, Juhu

by Parinee Vir Bhuvan Redevelopment Private Limited · Juhu, Mumbai 400049 · Map

Launched
Jun 20224 yrs 3 mths promised
Possession (MahaRERA)
Sep 2026Not extended
Concrete structure
0%Early stage
Booked
18 of 4144%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
13
4 BHK
28
Total units
41
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%18
100%0%0%–
100%0%0%–
100%0%0%18

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400049

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400049
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 3 mths7 yrs 5 mths
Possession date extendedNo1 of 4
Possession date (MahaRERA)Sep 2026Dec 2029
Concrete structure (RCC)0%100%
Units booked44%66%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Elenora by Parinee Vir Bhuvan Redevelopment Private Limited is a 41-unit MHADA-sanctioned project in Juhu, Mumbai 400049, launched in June 2022 with possession due in September 2026. 18 units booked out of total 41 units. Work on the concrete structure (RCC) has not started.

Read full summary

Elenora is a MHADA-sanctioned project by Parinee Vir Bhuvan Redevelopment Private Limited in Juhu, Mumbai 400049, registered with MahaRERA as P51800046382. It was launched in June 2022. It has 41 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in September 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.

18 units booked out of total 41 units (44%).