Green Acres, Juhu

by Shree Mahavir Estate Green Acres · Juhu, Mumbai 400049 · Map

Launched
Jun 20227 yrs 6 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
85%Mid-construction
Booked (free sale)
17 of 2959% · 35 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale17 booked out of 29 units

Rehab35 units for existing members

Total 64 units. Rehab units are not for sale.

Project facts

3 BHK
38
4 BHK
26
Total units
64
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
29
Rehab units
35

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 57%Jul 2026: Concrete structure (RCC) 85%Oct 2026: Concrete structure (RCC) 85%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 5%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 85%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%10%17
100%85%5%15
100%57%0%11
100%5%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400049

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400049
MeasureThis projectSimilar projects
Launch to possession (as first promised)7 yrs 6 mths4 yrs 3 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)Dec 2029Dec 2026
Concrete structure (RCC)85%100%
Units booked (free sale)59%44%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Green Acres by Shree Mahavir Estate Green Acres is a 64-unit MHADA-sanctioned project in Juhu, Mumbai 400049, launched in June 2022 with possession due in December 2029. 17 units booked out of 29 units for sale. The concrete structure (RCC) is 85% complete.

Read full summary

Green Acres is a MHADA-sanctioned project by Shree Mahavir Estate Green Acres in Juhu, Mumbai 400049, registered with MahaRERA as P51800045666. It was launched in June 2022. It has 64 units in 2 buildings, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 64 units, 29 are for sale and 35 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 85% complete, final finishes 10% complete.

17 units booked out of 29 units for sale (59%). Since the July 2026 update, 2 more units have been booked.