Shelton Elite, Juhu
by Marriott Realtors Private Limited · Juhu, Mumbai 400049 · Map
- Launched
- Sep 20223 yrs 6 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 9 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 8 of 3126% · 16 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale8 booked out of 31 units
Rehab16 units for existing members
Total 47 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 2
- 3 BHK
- 28
- 4 BHK
- 16
- Total units
- 47
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 31
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 31% | 8 | |
| 100% | 100% | 7% | 3 | |
| 100% | 81% | 1% | – | |
| 100% | 43% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400049
Projects with 20–100 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 6 mths | 7 yrs 4 mths |
| Possession date extended | By 9 mths | 0 of 5 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2029 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 26% | 74% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- New Brindavan CHSL, Juhu
- Elenora, Juhu
- Green Acres, Juhu
- Park Grandeur, Juhu
- Maestro, Juhu
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| New Brindavan CHSL | August 2022 | December 2029 | 100% | 8 units booked out of 10 units for sale |
| Elenora | June 2022 | September 2026 | 0% | 18 units booked out of total 41 units |
| Green Acres | June 2022 | December 2029 | 85% | 17 units booked out of 29 units for sale |
| Park Grandeur | May 2022 | December 2029 | 100% | 39 units booked out of 53 units for sale |
| Maestro | May 2023 | November 2026 | 100% | 27 units booked out of total 35 units |
About this project
Shelton Elite by Marriott Realtors Private Limited is a 47-unit MHADA-sanctioned project in Juhu, Mumbai 400049, launched in September 2022 with possession due in December 2026. 8 units booked out of 31 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shelton Elite is a MHADA-sanctioned project by Marriott Realtors Private Limited in Juhu, Mumbai 400049, registered with MahaRERA as P51800046724. It was launched in September 2022. It has 47 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 47 units, 31 are for sale and 16 are rehab units for existing members.
Its registered possession date is December 2026, extended by 9 months from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes 31% complete.
8 units booked out of 31 units for sale (26%). Since the July 2026 update, 5 more units have been booked.