Skip to main content

Paranjape Aspire, Andheri West

by Psc Realtors Private Limited · Andheri West, Mumbai 400053 · Map

Launched
Jun 20224 yrs 9 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
61%Mid-construction
Booked (free sale)
73 of 9081% · 37 rehab units
Buildings
10.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale73 booked out of 90 units

Rehab37 units for existing members

Total 127 units. Rehab units are not for sale.

Project facts

1 BHK
39
2 BHK
82
Other units
6
Total units
127
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
1
Free-sale units
90
Rehab units
37

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)61%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 40%Dec 2025: Concrete structure (RCC) 61%Jul 2026: Concrete structure (RCC) 61%Oct 2026: Concrete structure (RCC) 61%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 61%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%61%0%73
100%61%0%73
100%61%0%73
100%40%0%38

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400053

Projects with 60–250 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 9 mths3 yrs 9 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Mar 2027Jun 2026
Concrete structure (RCC)61%100%
Units booked (free sale)81%70%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Paranjape Aspire by Psc Realtors Private Limited is a 127-unit MHADA-sanctioned project in Andheri West, Mumbai 400053, launched in June 2022 with possession due in March 2027. 73 units booked out of 90 units for sale. The concrete structure (RCC) is 61% complete.

Read full summary

Paranjape Aspire is a MHADA-sanctioned project by Psc Realtors Private Limited in Andheri West, Mumbai 400053, registered with MahaRERA as P51800045731. It was launched in June 2022. It has 127 units in 1 building: 121 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 127 units, 90 are for sale and 37 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 61% complete, final finishes not started.

73 units booked out of 90 units for sale (81%).