Codename Rare By Runwal, Andheri West

Ready to moveLapsed

by Runwal Developers Ltd · Andheri West, Mumbai 400053 · Map

Launched
Apr 20224 yrs 2 mths promised
Possession (MahaRERA)
Jun 2026Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
66 of 6897%
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
17
3 BHK
51
Total units
68
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 12%Dec 2025: Concrete structure (RCC) 40%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 90%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%66
100%100%90%66
100%40%0%65
100%12%0%47

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400053

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 2 mths3 yrs 6 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)Jun 2026Dec 2026
Concrete structure (RCC)100%100%
Units booked97%62%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Codename Rare By Runwal by Runwal Developers Ltd is a 68-unit MHADA-sanctioned project in Andheri West, Mumbai 400053, launched in April 2022; its MahaRERA registration has lapsed. 66 units booked out of total 68 units. The concrete structure (RCC) is complete.

Read full summary

Codename Rare By Runwal is a MHADA-sanctioned project by Runwal Developers Ltd in Andheri West, Mumbai 400053, registered with MahaRERA as P51800034594. It was launched in April 2022. It has 68 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

66 units booked out of total 68 units (97%).

Runwal's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA46
Total units across these projects14,623
Completed without extending the possession date10
Completed after an extension5
Lapsed5
Under construction26
Possession date extended on the builder's application16
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Runwal projects343 (35 of 46 projects)

See all Runwal projects →